Board of Contract Appeals
                    General Services Administration
                         Washington, D.C. 20405
 
 
                       _________________________
 
                      DENIED:  September 22, 2000
                       _________________________
 
 
                              GSBCA 14165
 
 
                  WESTERN AVIATION MAINTENANCE, INC.,
 
                                           Appellant,
 
                                   v.
 
                    GENERAL SERVICES ADMINISTRATION,
 
                                           Respondent.
 
        Otto S. Shill, III, Bradley D.  Weech, and Kelly G. Black of
   Jackson White Gardner Weech & Walker, P.C., Mesa, AZ, counsel for
   Appellant.
 
        Michael  J.   Noble,  Office  of  General  Counsel,  General
   Services Administration, Washington, DC, counsel for Respondent.
 
   Before Board Judges BORWICK, DeGRAFF, and GOODMAN.
 
   DeGRAFF, Board Judge.
 
        The General  Services Administration (GSA) entered into five
   contracts to sell five airplanes to Western Aviation Maintenance,
   Inc. (Western Aviation).   GSA did not deliver  the airplanes and
   Western  Aviation sued  for breach  of contract.   In  an earlier
   opinion, Western  Aviation Maintenance, Inc. v.  General Services
   Administration,  GSBCA 14165,  98-2 BCA    29,816,  we  held that
   Western Aviation is  not entitled to specific  performance of its
   contracts.   We  now  hold  that, even  though  GSA breached  its
   contracts  with  Western  Aviation,  Western  Aviation   has  not
   established that it is entitled  to recover any damages for those
   breaches.
 
                            Findings of Fact
 
   GSA Issues an Invitation for Bids
 
        In early  1996, GSA  issued an invitation  for bids  for ten
   surplus  airplanes.    The airplanes  had  been  declared surplus
   property by  the Department of  State and were in  the custody of
   the United States Air  Force.  Exhibits 1,  11, 24.  The task  of
   selling these airplanes  was among the duties of  a warranted GSA
   contracting officer whose responsibilities included disposing  of
   property  that  had been  screened  to  determine  that no  other
   Government  agency had  a  use  for  it and  that  there  was  no
   qualified party to whom the Government could donate the property.
   Transcript at 5-8, 28-29.  The airplanes listed in the invitation
   for  bids had  cleared that  utilization  and donation  screening
   process.  Exhibit 24; Transcript at 5-8.
 
 
        The invitation listed the airplanes' serial numbers and said
   that they were C-123s manufactured  by Fairchild in 1954 or 1955.
   The  title page of  the invitation contained  the heading, "Scrap
   and  Salvage  Aircraft,"  and  the  invitation  stated  that  the
   airplanes had been  cannibalized to varying degrees  and had been
   exposed to the elements.  Exhibit 1.  GSA's regulations explained
   that "scrap" property had no  value other than its basic material
   content, and  that "salvage" property had some value greater than
   its basic material content, although  its condition was such that
   its repair or rehabilitation  would cost in excess of 65%  of its
   acquisition cost.  41 CFR 101-43.001-28, -29 (1995).   Generally,
   salvage airplanes contain some usable components, scrap airplanes
   are useful  only  for  their material  content,  and  neither  is
   suitable for  flying.   Transcript at  230.   Whether a scrap  or
   salvage airplane  can be  retrofitted or upgraded  so that  it is
   flyable is  a  function of  the amount  of work  that someone  is
   willing to do  in order to obtain the  necessary Federal Aviation
   Administration  (FAA)  approvals.   Although some  airplanes have
   been sold for scrap or salvage  and then been modified to  become
   airworthy, GSA  had no expectation  that a  purchaser would  make
   these airplanes flyable.  Transcript at 233, 237.  The invitation
   stated that  GSA did  not represent that  the airplanes  could be
   modified  to meet  FAA  standards  for  airworthiness,  and  told
   prospective purchasers  who contemplated operating  the airplanes
   in  the  United  States  to  consult  the  FAA  before  making  a
   commitment to purchase the airplanes.  Exhibit 1. 
 
          The  Defense  Logistics Agency  (DLA)  determines property
   disposal policy  for the Department  of Defense (DoD).   When GSA
   advertised  the  C-123s for  sale,  DLA  had  issued the  Defense
   Reutilization and  Marketing Manual,  which contained  a list  of
   types of  airplanes that were  available for sale  for commercial
   use.  The manual was an internal DoD document that applied to DoD
   activities.  Exhibits 12, 26, 136.  Before GSA advertised the  C-
   123s for sale, the  director of the property management  division
   for GSA Region 9  consulted the person at DLA who was responsible
   for  maintaining and  issuing the  list  of commercially  salable
   airplanes.   Transcript  at  87-88.   That  individual said  that
   although the C-123  was not yet  listed as an item  available for
   sale  for commercial use, a decision had been made to classify it
   as commercially salable and it would  be listed as such the  next
   time that the  manual was revised.  Subsequently,  GSA issued the
   invitation for bids.   Exhibit 12; Transcript  at 14, 88.   After
   the  sale  at  issue   in  this  appeal  occurred,  the   Defense
   Reutilization and Marketing Manual was  revised and listed the C-
   123 as an item available for sale for commercial use.  Transcript
   at 68-69; Exhibits 26, 136.  
 
 
        The  invitation for  bids incorporated  Standard Form  114C,
   General  Sale Terms  and  Conditions,  which  provided  that  the
   purchaser was  entitled to obtain the property  upon full payment
   therefor,  unless the  invitation stated otherwise.   Exhibits 1,
   2.    The  invitation  did  not  place  any  limitations  upon  a
   purchaser s ability  to obtain the  property, except to  say that
   the purchaser had to arrange for a  removal date and time to load
   or tow the airplanes from the base, and to coordinate the removal
   with  the  Government s property  custodian.    Exhibit  1.   The
   purchaser  could either move  the airplanes or  make arrangements
   with a nearby contractor to move them.   Exhibit 1; Transcript at
   101, 248-49.   Form 114C explained that  if a purchaser failed to
   remove  its property,  the  Government  could  send a  notice  of
   default and give  the purchaser the option to cure the default by
   removing the property within a specified time.  Exhibit 2. 
 
        In the invitation for bids, GSA warranted that  the property
   listed in the  invitation would conform to its  description.  The
   invitation then stated:
 
        DESCRIPTION  WARRANTY: .  . .  If  a misdescription  is
        determined  before   removal  of   the  property,   the
        Government  will keep the property and refund any money
        paid.  If a misdescription is determined after removal,
        the  government will  refund  any  money  paid  if  the
        purchaser takes the property at his or her expense to a
        location  specified by the  contracting officer. .  . .
        The  amount of recovery under this provision is limited
        to  the purchase  price of  the misdescribed  property.
        The purchaser is not entitled  to any payment for  loss
        of  profit or any other money damages, special, direct,
        indirect, or consequential.
 
   Exhibit 1.
 
        Form 114C contained the following clauses:
 
        15.  LIMITATION ON GOVERNMENT S LIABILITY
 
        Except   for    reasonable   packing,    loading,   and
        transportation  costs   (such  packing,   loading,  and
        transportation  costs  being  recoverable only  when  a
        return of property at  Government cost is  specifically
        authorized  in writing by  the Contracting Officer) the
        measure of the Government s liability in any case where
        liability of the  Government to the Purchaser  has been
        established  shall not exceed refund of such portion of
        the purchase price as the Government may have received.
 
        22.  WITHDRAWAL OF PROPERTY AFTER AWARD
 
        The Government reserves  the right to withdraw  for its
        use  any  or  all  of  the  property  covered  by  this
        contract, if a  bona fide requirement for  the property
        develops  or  exists  prior to  actual  removal  of the
        property from  Government control.   In the event  of a
        withdrawal under  this condition, the  Government shall
        be liable only for the  refund of the contract price of
        the  withdrawn property or such portion of the contract
        price as it may have received.
 
   Exhibit 2.
 
        The invitation for bids also incorporated Standard Form 114-
   C-1, Special Sealed Bid Conditions, which provided:
 
        D.  AWARD OF CONTRACT
 
        The contract will be awarded to that responsible Bidder
        whose bid  conforming to  the Invitation  will be  most
        advantageous to the Government, price and other factors
        considered.    A  written  award  mailed (or  otherwise
        furnished) to the successful Bidder within the time for
        acceptance provided  in the Invitation  shall be deemed
        to result  in a  binding contract  without any  further
        action by either party.
 
   Exhibits 1, 3.
 
        The invitation  stated that potential bidders  could inspect
   the  airplanes  at Davis-Monthan  Air  Force  Base, which  is  in
   Tucson, Arizona, in early  February 1996, and submit  sealed bids
   later that month.  Bidders  were required to submit a deposit  of
   twenty percent of their bids,  and the successful bidder would be
   required to pay  the remaining balance  within ten calendar  days
   after award of a contract.  Exhibits 1, 11, 24. 
 
   GSA Awards Five Contracts to Western Aviation
 
        Western Aviation, which is owned  in part by Floyd Stilwell,
   owns and operates  aircraft primarily for  use in fire  fighting.
   Mr.  Stilwell  also owns  part  of  Marsh  Aviation, which  is  a
   manufacturing  company  that  repairs, overhauls,  rebuilds,  and
   modifies aircraft.  Transcript at 110, 157.  Western Aviation and
   Marsh Aviation are located in the same facility in Mesa, Arizona,
   but  they  are   separate  companies  with  different   corporate
   charters.  Exhibits  4, 109; Transcript at 114-15.   Mr. Stilwell
   is the  president of  Western Aviation  and  the chief  executive
   officer of Marsh Aviation.  Transcript at 175.  The two companies
   vigorously  maintain  separate  books  and  records,  and    have
   separate business  operations as  a mechanism  for limiting  each
   company's potential liability.  Transcript at 114, 175-76.  
 
        When Mr.  Stilwell saw  the invitation for  bids for  the C-
   123s, he immediately made arrangements to see the airplanes.  Mr.
   Stilwell  was  interested in  the  airplanes because  he  and the
   person  who  holds  the  design  rights to  the  C-123  had  been
   discussing ways to upgrade the engines on the C-123 and equip the
   airplane so that it could be used  for fighting forest fires.  In
   Mr. Stilwell's opinion, there was an opportunity to use C-123s to
   produce   a  3000  gallon  tanker  aircraft  that  would  compete
   successfully  for fire fighting contracts.  Transcript at 116-17.
   Mr. Stilwell went to see the C-123s twice before Western Aviation
   made a bid for them.  Transcript at 117-18.  He went inside seven
   airplanes,  including  five   airplanes  that  Western   Aviation
   subsequently purchased.   Transcript  at 249.   Western  Aviation
   submitted its bid, signed by  Mr. Stilwell, for ten airplanes and
   its accompanying deposit  on February 26, 1996.   The bid  stated
   that Western Aviation would pay for the airplanes and remove them
   within thirty days after the bid opening date.  Exhibit 4. 
 
        On February 29, 1996, GSA  opened the bids for the airplanes
   and determined  that   Western Aviation was  the high  bidder for
   five of the  airplanes.   Exhibits 4, 5.   Mr. Stilwell  recalled
   that, before  he received  written notice  of Western  Aviation's
   high bids, he telephoned the contracting officer and learned that
   Western  Aviation was the  successful bidder for  five airplanes.
   Transcript  at  121-22.   On  March  7,  1996, GSA  sent  Western
   Aviation  five notices  of  award  signed  by  GSA's  contracting
   officer.  Each notice stated that after Western Aviation paid the
   balance due  for each  airplane, GSA would  issue a  receipt that
   would authorize Western Aviation to remove the  airplane from the
   base.  The  notices also stated that Western  Aviation had to pay
   the balances  due and  remove the  airplanes  by March 21,  1996.
   Exhibit  6.  Western Aviation paid the  balances due by the March
   21 deadline.   The total price  paid by Western Aviation  for the
   five airplanes  was $87,500.   The receipt  that GSA  provided to
   Western Aviation stated  that the airplanes would be  released at
   the request of Western Aviation.  Exhibit 8.
 
        The  evidence  does  not  establish  that,  at the  time  of
   contracting,  GSA had  any  reason  to  anticipate  that  Western
   Aviation intended to refurbish the  C-123s and equip them so that
   they could be used for fighting fires.  The GSA employees did not
   know either Western Aviation's intentions regarding the airplanes
   or  its general  line  of  business.   This  was the  contracting
   officer s first involvement  with a sale of airplanes  and he did
   not  know what  Western  Aviation s  business was.    He did  not
   remember having any contact with  Mr. Stilwell before the sale at
   issue   here   was  completed.[foot #] 1     Transcript   at  23-
   24, 30-31, 246.  The director of the property management division
   for  GSA  Region  9  had  a conversation  with  Mr.  Stilwell  in
   approximately  1995, concerning  a problem  that  arose when  GSA
   transferred some  C-130 airplanes to  another Government  agency.
   Mr. Stilwell  told her that he  was in the  business of providing
   either  equipment or  services to  be  used in  fire suppression.
   They did  not discuss the source  of the airplanes that  he used.
   She  had no other  contacts with Mr. Stilwell  before the sale at
   issue in this  appeal, and before the contracts  were awarded she
   had no  idea what Western  Aviation's operations were.   In fact,
   she  associated the  name "Western"  with  an entirely  different
   company.   Transcript  at  89-92, 231,  233-34.   GSA s  property
   disposal and  aircraft utilization  specialist  had some  contact
   with Mr.  Stilwell before the  sale at issue.   Transcript at 98.
   She knew that  Marsh Aviation was re-engining some  airplanes for
   the   State of  California, but  she had never  heard of  Western
   Aviation.   Transcript  at 240-41.   According  to Mr.  Stilwell,
   before the  sale at  issue in this  appeal, he  did not  tell the
   contracting  officer  what   Western  Aviation s  business   was.
   Transcript  at 162-63.    In  addition, when  he  spoke with  the
   director of  the property management  division for GSA  Region 9,
   Mr. Stilwell represented himself as  working for Marsh  Aviation.
   Transcript at 163-64.   Also according to Mr.  Stilwell, prior to
   the  sale,  GSA s  property  disposal  and  aircraft  utilization
   specialist  probably  did  not know  what  Western  Aviation did.
   Transcript  at 164.   Mr.  Stilwell testified  that, before  this
   sale, he had dealt  with GSA probably six to  ten times.  He  did
   not say that  he dealt  with GSA on  behalf of Western  Aviation.
   Transcript at 110-11.
 
 
        After the contracts  were awarded, Mr.  Stilwell and one  or
   two  of his technicians came to see the airplanes.  Transcript at
   98-99; 122.  On their first trip, they determined what they would
   need to do in order  to make the airplanes  ready to be flown  to
   Mesa.  Transcript  at 122.  On  a subsequent trip, they  measured
   the interior of the airplanes  so that they could determine where
   to  place  the  tanks  that  would hold  3,000  gallons  of  fire
   retardant material,  and how they  could install the  door system
   that would  be used to  deliver the fire retardant  material from
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 1 Mr. Stilwell thought that the contracting officer
   visited his  facility in 1993  or 1994, and  saw work that  Marsh
   Aviation  was  performing.    Transcript  at  250-51.    Even  if
   Mr. Stilwell's recollection  is correct, this does  not establish
   that  the   contracting  officer  knew   anything  about  Western
   Aviation.
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   the  airplanes.   Transcript at  122-25.   They  went inside  the
   airplanes several times.  Transcript at 100, 103-04.  In order to
   fly the  airplanes after he  made his planned  modifications, Mr.
   Stilwell would  have  needed   to comply  with all  of the  FAA's
   requirements  for making structural changes and would have needed
   to obtain  a supplemental  type certificate  from the  FAA, which
   would  have  allowed  the  airplanes  to  be flown  as  modified.
   Transcript at 124, 140-42.   
 
 
        Mr. Stilwell explained that contracts to lease airplanes for
   fire fighting are awarded  every three years.   Because contracts
   were to be  awarded early the following year,  Mr. Stilwell had a
   short time within which to modify the airplanes, obtain the FAA s
   approval for modifying the airplanes, and bid to supply airplanes
   for  fire  fighting  contracts.   As  soon  as  Western  Aviation
   received award of the contracts  for the five airplanes, he began
   designing a door system  and a tank system that would  fit in the
   airplanes and operate satisfactorily.   Transcript at 133-39.   A
   month  or so  after the  designs were  developed, Marsh  Aviation
   began building the tank and door system.  Transcript at 134, 159.
   Mr. Stilwell testified that Western Aviation signed a  work order
   for Marsh  Aviation to  design and retrofit  the airplanes,  that
   Marsh Aviation billed  Western Aviation for amounts due, and that
   Western  Aviation's obligation  to Marsh  Aviation  was shown  in
   those bills.   The  record does not  contain a  copy of  the work
   order,  but it  does  contain  invoices  from Marsh  Aviation  to
   Western Aviation.  Exhibits 112, 113, 123; Transcript at 158-60. 
 
        GSA's property disposal and  aircraft utilization specialist
   accompanied Mr.  Stilwell and his  technicians when they  came to
   see the airplanes after  award.  She testified that she  was sure
   that she  and Mr. Stilwell  discussed what he was  planning to do
   with  the airplanes,  but she  did  not recall  exactly what  Mr.
   Stilwell told her.  Transcript at 99-100.  Mr. Stilwell testified
   that they  did not discuss  the "specific details" of  his plans,
   but that  they did  discuss that he  was taking  measurements and
   proceeding to manufacture  hardware.  Transcript at 128.   In the
   experience  of the director  of the property  management division
   for GSA  Region 9, it was not the norm  for a purchaser to expend
   large  amounts  of  money before  taking  delivery  of airplanes.
   Transcript at 234-35.  
 
   A Possible Contamination Problem Arises 
 
        In  April 1996,  GSA notified the  Air Force of  the sale of
   nineteen C-123 airplanes.  These  included the ten airplanes that
   GSA advertised for sale in early 1996, five of which were sold to
   Western Aviation, plus nine additional C-123s that the  Air Force
   transferred to GSA in February  1996.  Exhibits 9, 39; Transcript
   at  34.  On  June 6, 1996,  the Air Force  wrote a  letter to GSA
   concerning the  nineteen C-123s.   The letter explained  that the
   Air Force had to "demilitarize"  the airplanes before they  could
   be released.  During that process, its employees smelled chemical
   odors and experienced a burning  sensation when working in two of
   the airplanes, neither one of which had been purchased by Western
   Aviation.    The  June  6  letter explained  that  the  airplanes
   possibly contained  hazardous chemicals  and that  the Air  Force
   could not release  the airplanes until they were  tested for such
   materials.  The  estimated cost of the tests  was between $12,500
   and $37,500 per airplane.  Exhibit 9.  
 
 
        According to  the Air Force official in  charge of disposing
   of the  airplanes, the two  airplanes in which  employees smelled
   chemical  odors and experienced a burning sensation were equipped
   with spray equipment.   Transcript at 40.   In order to determine
   whether an airplane has been used for spraying, the Air Force can
   inspect  either  the  airplane  itself  or  the  records  of  the
   airplane.  Transcript  at 213.  The Air Force  official in charge
   of disposing of the nineteen  C-123s did not recall precisely how
   many of  them had spray equipment, and  he did not recall whether
   those with spray equipment were among the airplanes purchased  by
   Western Aviation.   Transcript  at 37,  215-16.   Mr.  Stilwell's
   recollection  was that  only  two of  the  five Western  Aviation
   airplanes were equipped  with spray  tanks.   Transcript at  118.
   The records of  the nineteen C-123s do not show what use was made
   of the spray  equipment, but the Air Force  was concerned that it
   might   have  been  used  to  spray  defoliants  or  insecticides
   containing harmful chemicals.  Exhibit  42; Transcript at 64.  As
   a  result of  the  odors  and burning  sensation,  the Air  Force
   required personnel to  wear protective gear  when working in  the
   airplanes that  had spray equipment.   Exhibit 29;  Transcript at
   39.  
 
        In early June 1996, the director of the  property management
   division for GSA's Region 9  telephoned Mr. Stilwell and told him
   that there was  going to be a delay in completing the sale of the
   airplanes to Western Aviation.   She explained that the delay was
   due    to   suspected    dioxin[foot #] 2   contamination,    and
   she offered Mr.  Stilwell the option  of canceling the  contracts
   and receiving a refund from GSA.   Mr. Stilwell said that he  was
   willing  to  wait   and  see  whether  the   situation  could  be
   resolved.[foot #] 3  Transcript at 91-92, 235.  At that time, the
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 2 Dioxins are a family of related chemicals and are
   a common  contaminant in  Agent Orange.   Transcript at  81, 189,
   193,  198; Exhibit  46.   Agent  Orange  is a  herbicide that  is
   largely made  up of  two herbicides commonly  known as  2,4-D and
   2,4,5-T.   Transcript  at  196;  Exhibit  46.    Although  dioxin
   toxicity   is  documented   in   laboratory  animals,   there  is
   disagreement in the scientific  community concerning the toxicity
   of dioxin in humans.  Transcript at 190-91; Exhibit 46.  
 
        [foot #] 3 Mr.   Stilwell's   recollection  was   that   GSA
   initially told him that the  Air Force would have to demilitarize
   the   airplanes,  and   later  told   him   about  the   possible
   contamination problem.  Transcript at 164-65.  To the extent that
                                                      (continued...)
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   director of  the property  management division  for GSA  Region 9
   hoped that GSA would  be able to deliver the airplanes to Western
   Aviation.  Transcript  at 235.  She spoke  with Mr. Stilwell once
   or twice more, in  order to keep in touch and  to continue to let
   him know that GSA was willing to refund Western Aviation's money.
   Transcript at 93.  
 
 
        At some point, probably in June, GSA's property disposal and
   aircraft  utilization  specialist  notified  Mr.  Stilwell   that
   Western Aviation could come and pick up two of the five airplanes
   that  it had  purchased.   She  told Mr.  Stilwell that  he could
   retrieve  two  of  the  airplanes  because  the  Air   Force  had
   determined  that  they had  not  been  used  for spraying.    Mr.
   Stilwell responded that he did not want  to come and pick up only
   two of the airplanes, and that  he would rather come and pick  up
   all  five at  once.   Transcript  at 100-01,  241.   Mr. Stilwell
   explained  that it is expensive to set up an operation to prepare
   airplanes to  be moved, and  that he wanted  to do this  only one
   time.    Transcript  at  129, 252-53.    When  this  conversation
   occurred,  GSA's  property  disposal   and  aircraft  utilization
   specialist's understanding was that the delivery of the remaining
   three  airplanes was on  hold, and not  that they would  never be
   released.  Transcript at 244.  
 
        The Air Force  took swipe samples from some  of the nineteen
   C-123  airplanes  and  had those  samples  analyzed  to determine
   whether  the planes  were contaminated with  hazardous materials.
   Exhibits 30, 31.  Two swipe samples were taken in May and sent to
   a laboratory  to be  analyzed for dioxins  in August.   Traces of
   dioxins were  found in the samples.   The record of  the analysis
   does  not say  which  airplanes  were the  subject  of the  swipe
   samples.   Exhibits 31, 46;  Transcript at 194.   Also in August,
   swipe  samples  from  seventeen C-123s,  including  three  of the
   airplanes purchased by Western Aviation, were taken and were sent
   to a laboratory to  be analyzed for 2,4-D  and 2,4,5-T.   Exhibit
   30.   The  Air  Force  official in  charge  of  disposing of  the
   airplanes  believed  that samples  were  taken  from all  of  the
   airplanes equipped with  spray apparatus.  Transcript at  46.  On
   each  of the seventeen airplanes tested,  samples were taken from
   two locations where the presence  of 2,4-D and 2,4,5-T would have
   been most likely.   Transcript at 78-80.  The amount,  if any, of
   the two herbicides  in the samples  taken from  one of the  three
   Western Aviation airplanes was less than could be detected by the
   analysis to which they were subjected.  For each of the other two
   airplanes,  one sample showed detectable levels of herbicides and
   the other sample did not.  Exhibit 30; Transcript at 198-99, 203-
   05.    The  laboratory that  analyzed  the  August swipe  samples
   explained that  the presence of  2,4-D or 2,4,5-T  suggested, but
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 3 (...continued)
   this conflicts with the testimony of the director of the property
   management division, it is irrelevant to our disposition of  this
   appeal.  
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   did not prove, the  presence of dioxin.   Exhibit 30 at 22.   The
   Air  Force   toxicologist  who   studied  the   results  of   the
   laboratory's analysis concluded that there was some dioxin in the
   airplanes  that  were  tested.    Transcript at  198.    He  also
   concluded that the level of contamination of individual airplanes
   was unknown, and he recommended that a minimum of ten samples per
   airplane be taken and analyzed in order to determine the level of
   dioxin contamination  of the  airplanes.   He  estimated that  it
   would cost approximately $15,000  to evaluate each airplane.   He
   also  recommended that airplanes with detectable levels of dioxin
   be  fully   decontaminated  before  being   transferred,  and  he
   explained that the cost of decontamination was unknown.   Exhibit
   46.  
 
 
        Mr.  Stilwell spoke with GSA's contracting officer and GSA's
   property  disposal and  aircraft  utilization specialist  several
   times in the fall  and asked what was happening  with the release
   of  the airplanes.   The  contracting officer  said that  the Air
   Force had  not yet released  the airplanes, but Mr.  Stilwell did
   not get the impression that Western  Aviation would never receive
   the  airplanes.  Transcript at 146.   During the fall months, the
   Air  Force was  trying to  decide whether  it should  release the
   airplanes, test  them  further, attempt  to  decontaminate  them,
   destroy them, or seal them and leave them in place.  Exhibits 32-
   39.  
 
        On December 18,  1996, the Air  Force wrote a letter  to GSA
   concerning  ten C-123s, including the five airplanes purchased by
   Western  Aviation.   The  letter stated  that the  airplanes were
    possibly  contaminated with dioxin   and asked GSA  to terminate
   the  sale  due  to   public  health concerns.     The  Air  Force
   explained  that one  of the  ten C-123s  had tested  positive for
   dioxin, and that it was   prohibitively expensive  to test all of
   the  airplanes properly.    The  letter stated  that  two of  the
   airplanes  sold to  Western Aviation had  been used  in Southeast
   Asia and  that no records  were available  to show how  the other
   airplanes had been used.  In addition, the letter stated that the
   C-123s should have  never been advertised  for sale because  they
   did  not appear  on  the list  of commercially  salable airplanes
   appended  to  the  Defense Reutilization  and  Marketing  Manual.
   Exhibit 10.   After  sending this  letter to  GSA, the  Air Force
   continued to consider whether it would be possible to release the
   airplanes.  Exhibits 40-43. 
 
   GSA Terminates the Contracts
 
        On  January 8,  1997,  GSA  terminated  its  contracts  with
   Western  Aviation because  the  Air Force  would not  release the
   airplanes  due  to concerns  about possible  dioxin contamination
   and,  therefore,  GSA could  not  deliver  the  airplanes.    GSA
   explained that it would refund Western Aviation s purchase price.
   Exhibit  13;  Transcript  at  18, 22.    The  contracting officer
   understood  that  the Air  Force did  not have  any need  for the
   airplanes,  and that  it intended  to seal  up the  airplanes and
   store them.  Transcript at 29.  
 
 
        Until  Mr.  Stilwell  received GSA's  January  8  letter, he
   believed that he was going to be able to take at least two of the
   airplanes.  Transcript  at 146-47.  On January  13, 1997, Western
   Aviation objected to the termination  of its contracts.   Western
   Aviation explained  that it had spent  a great deal of  money and
   time  to design  a  fire  retardant  system  for  the  airplanes.
   Western Aviation  also said that  it would be  willing to  sign a
   release to protect the  Air Force from  any damage that it  might
   incur.  Exhibit 14.
 
        The Air Force  wrote to Western Aviation on  March 12, 1997,
   and stated that it could not release the airplanes.  According to
   the Air  Force s letter, three  of the airplanes sold  to Western
   Aviation were  used in  Southeast Asia and  all of  the airplanes
   contained spray  apparatus, which led  the Air Force  to conclude
   that all  of the  airplanes might  possibly be  contaminated with
   dioxin.  The  Air Force explained that it  would be prohibitively
   expensive  to  test  the  airplanes  in  order  to   confirm  any
   contamination,  and also explained that there were no established
   remediation  goals  or  acceptable  clean-up  levels  for  dioxin
   contamination.  Exhibit  17.  The Air Force  sealed the airplanes
   and stored them  at Davis-Monthan Air Force Base.   Transcript at
   218.  GSA  refunded Western Aviation's  purchase price.   Exhibit
   19.
 
   Western Aviation Claims Damages
 
        In  letters to  GSA  dated  March 7  and  19, 1997,  Western
   Aviation again objected to the  termination of the contracts.  In
   the March 19 letter, Western Aviation explained that it had spent
   over $110,000  in order to develop and to market a fire retardant
   system to be used  in the C-123s for aerial forest fire fighting.
   The letter did not say what  costs were included in the $110,000.
   Western Aviation also said that it had paid interest in excess of
   $8000 during the  time that GSA  held Western Aviation's  payment
   for  the airplanes.  Western Aviation stated that it wanted to be
   made whole if  GSA could not perform the contracts.  Exhibits 16,
   21.   GSA responded that  its liability was limited  to refunding
   Western Aviation s purchase  price and denied Western  Aviation s
   request for any additional money.   Exhibit 22.  Western Aviation
   later certified a claim for damages of $500,000, but did not  say
   what costs were included in that figure.  Exhibit 84. 
 
        In the complaint filed in this case, Western Aviation stated
   that it had invested over $500,000 in its C-123 project.  It said
   that its damages  consisted of the  cost of arranging for  a work
   facility near  Davis-Monthan Air  Force Base, purchasing  special
   equipment to work on the airplanes, designing and building a tank
   with  a micro-processor controlled door system, developing an FAA
   certification plan, researching the availability of and obtaining
   spare  parts, creating  a marketing  and financing plan,  and the
   cost of  financing $87,500 for one  year.  The  complaint did not
   set  out the costs that made up  any of these individual elements
   of damage.  Exhibit 74.  
 
 
        In its responses to  GSA's interrogatories, Western Aviation
   stated  that its  damages  included the  cost  of inspecting  the
   airplanes and preparing them to be removed from Davis-Monthan Air
   Force Base; purchasing  an aircraft tug and a tow  bar; travel to
   move the tow bar  from Davis-Monthan Air Force Base and  to store
   it in Tucson, and travel to move the tow bar to  Mesa; developing
   a sales program for the engines and propellers, and defaulting on
   the sale  of the engines  and propellers; research and  travel to
   locate  and  to bid  on  replacement  engines  and equipment  for
   upgrading  the C-123s; purchasing a prototype C-123; studying the
   design of  an engine  upgrade; designing  and developing  a tank;
   developing an FAA certification plan; multiple trips to Tucson to
   inspect and  evaluate the  five  C-123s; interim  storage of  the
   airplanes for  preparation for flight  to Mesa; and  developing a
   marketing program.   The interrogatory responses did  not set out
   the cost of any of these individual  elements of damage.  Exhibit
   114.  
 
        In a  September 4, 1998  letter to counsel for  GSA, Western
   Aviation  stated  that  its damages  consisted  of  the following
   elements and amounts:
 
        Marsh Aviation invoice dated March 8, 1997
                            Parts                    $  28,468.63
                            Mileage                      705.00
                            Labor                      179,600.00
                  Total                              $208,068.63
 
        Floyd Stilwell services 2/5/96 - 3/8/97
                                                     $100,000.00
        Tim Austin services 3/1/96 - 3/8/97
                                                          120,000.00
        Move Tim Austin from Florida to Arizona            8,000.00
        Move Tim Austin from Arizona to Florida            8,000.00
        Ghislain Boivin, travel and expenses                        
                                                          2,400.00
        Bob Gibson, deferred legal                                  
                                                          20,000.00
        Bill Walker, 1,000 hours 2/5/96 - 3/8/97                    
                                                               60,00
                                                               0.00
                  Total                              $318,400.00
 
   Exhibit 123.  
 
        The March  8, 1997  Marsh Aviation  invoice for  $208,068.63
   appended  to Western Aviation's September 4, 1998 letter contains
   a  list of  dollar amounts  paid  for supplies  ordered by  Marsh
   Aviation between March 5, 1996, and March 7, 1997, for a total of
   $28,468.63.   Exhibit 123.   Mr.  Stilwell  testified that  these
   supplies  were  used to  build  the  tank  and the  door  system.
   Transcript at 137-38.  Nearly  all of the $28,468.63 is supported
   by   invoices   from    Marsh   Aviation's   suppliers.[foot #] 4
   Exhibit 134;  Transcript at  168.  The  invoices show  that Marsh
   Aviation spent $4289.70  for supplies that were ordered after GSA
   terminated Western  Aviation's contracts.     Exhibits 123,  134.
   The record  does not contain  any explanation of the  $705 charge
   for mileage set  out in the Marsh Aviation invoice.   The invoice
   says  that the  $179,600 charge  for labor represents  3592 labor
   hours at $50 per hour.  Exhibit 123.  Attached to the invoice are
   time  sheets which Mr.  Stilwell testified represented  the hours
   spent by  the people who designed and fabricated the tank and the
   door system.  Transcript  at 150-51.  The  labor hours listed  on
   the time  sheets are  for time worked  between December  1995 and
   March 1997, and total nearly 6000 hours instead of the 3592 labor
   hours shown on  Marsh Aviation's March 8, 1997  invoice.  Exhibit
   123.  There is no explanation in the record of how Marsh Aviation
   decided which of the hours listed on its time sheets were devoted
   to work on Western Aviation's C-123 tank and door system.  
 
 
        Looking   next  at  the  $318,400  referred  to  in  Western
   Aviation's  September 4, 1998  letter, we find  no invoices, time
   sheets,  payroll records, bills, or any other documentary support
   for the  expenses included within  this amount.  The  September 4
   letter says  that between February  29, 1996, and March  8, 1997,
   Mr.  Stilwell spent  the majority  of his  time trying  to locate
   engines and  propellers that could  be installed in place  of the
   existing engines and  propellers on the C-123s,  trying to obtain
   financing for the FAA certification program, and working with Tim
   Austin  to develop  a  marketing  plan.   Mr.  Austin moved  from
   Florida to Arizona  to devote  all of  his time  to developing  a
   marketing  and  financing  program  for  converted  and  upgraded
   airplanes.  Bill Walker is a  test pilot who devoted his time  to
   FAA  certification requirements.   Bob Gibson is  an attorney who
   was hired to assist in obtaining financing and drafting contracts
   for  a C-123  program.   Ghislain Boivin  is the  president of  a
   company that intended  to act as an agent  to negotiate operating
   leases for the airplanes.  Exhibits 109 at 10-11; 123.  
 
        Other than the September 4, 1998 letter, there is nothing in
   the record to support the claimed  costs of $318,400.  During re-
   direct  examination,  Mr.  Stilwell's counsel  asked  him  if the
   damages  reflected in the  exhibits he  had testified  about were
   those of Western  Aviation.  Mr. Stilwell answered  that they are
   obligations  that Western  Aviation  has.    Transcript  at  179.
   Although Mr. Stilwell testified about  some of the attachments to
   the  September 4,  1998  letter,  he did  not  testify about  the
 
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 4 The  items not supported  by invoices  are $55.60
   listed as paid to DiEugenio; $87.30 listed as paid to Arizona Air
   Tool; and  $255.85 listed as  paid to Jorgensen Steel.   Exhibits
   112, 134.  
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   $318,400  or any  of the  expenses included  within that  figure.
   Transcript at 137-38, 150-51, 169. 
 
 
        In its  post-hearing brief, Western  Aviation claims damages
   of between  $4.2 and $18.7  million.  This includes  the $318,400
   discussed in the preceding paragraph, the $28,468.63 for parts as
   set out in the Marsh Aviation invoice discussed above dated March
   8, 1997, plus the following amounts:
 
        Labor costs                        $      369,825.00
        Computer costs                         20,686.94
        Equipment to move airplanes                   7,620.00
        Sale of parts from airplanes              298,550.00
        Sale or lease of airplanes
             Sale                          3.5 to 18 million
             Lease                            4.9 million
 
   Appellant s Post-Hearing Brief at 23-26.  
 
        In support of its  post-hearing claim of $369,825  for labor
   costs, Western  Aviation relies  upon a version  of the  March 8,
   1997  Marsh Aviation invoice  discussed above in  connection with
   the  damages calculation that  Western Aviation submitted  to GSA
   counsel  on September 4, 1998.  The  March 8 invoice that Western
   Aviation sent  to  GSA counsel  shows  labor costs  of  $179,600,
   representing  3592 hours of  work.  Exhibit 123.   The version of
   the March 8 invoice relied upon by Western Aviation in  its post-
   hearing  brief shows labor costs of $369,825, representing 7396.5
   hours of work.  Exhibit 112.  The record does not explain why two
   copies of  the same invoice  contain different figures  for labor
   costs and labor  hours.  In addition, the  documents that Western
   Aviation relies  upon in  its post-hearing  brief to support  the
   invoiced  7396.5 hours of  labor contain duplicative  entries, do
   not  support that  number of  hours, and  are different  from the
   documents  relied upon to support the number  of hours set out in
   the copy  of the invoice  that Western Aviation submitted  to GSA
   counsel on September 4, 1998.  Exhibits 123, 133.  
 
        In  support  of  its post-hearing  claim  of  $20,686.94 for
   computer costs,  Western Aviation relies  upon a copy of  a Marsh
   Aviation invoice that  lists amounts paid to  Transource Computer
   ($10,382.50),  to  A.R.P.  Inc.  ($13,810),   and  to  Courtaulds
   Aerospace  ($111.66).   Exhibit 113.   The  only evidence  in the
   transcript   concerning   computer-related   purchases   is   Mr.
   Stilwell's testimony:
 
        [W]e had to upgrade our  computers so that we could get
        the work  done in the  time frame we had  allocated for
        this program.  All our  work was done on computers with
        the  auto-CAD software  which  allows  you  to  do  two
        dimensional plotting and planning and drawings.
 
   Transcript  at  137.    The  record contains   two  invoices from
   Transource  Computer showing  that Marsh  Aviation purchased  two
   personal  computers in  January 1996,  for a  total of  $6765.28.
   Exhibit 134 at 64, 65.  There  are two invoices from A.R.P. Inc.,
   totaling  $13,810, for  consulting work  for  "water bomber  door
   control" engineering work  done for Marsh Aviation in  July 1996,
   and August  1997.   Exhibit  134 at  66, 68.   There  is also  an
   invoice  showing  that Marsh  Aviation  purchased something  from
   Courtaulds Aerospace  for $111.66 in  June 1997.  Exhibit  134 at
   67.   
 
 
        In support of its post-hearing  claim of $7620 for equipment
   to move airplanes, Western Aviation relies  upon Exhibits 130 and
   131, which  show that Marsh Aviation purchased a tow bar for $310
   on March 12, 1996, and a tow truck for $5750 in August  1996, and
   spent $1600 in October 1996, to have the tow truck shipped to its
   facility  in Mesa, Arizona.   Exhibits  130, 131.   Tow  bars are
   sometimes designed to be used with one specific type of airplane,
   and Marsh Aviation purchased its tow bar  in order to move the C-
   123s.  Transcript  at 102, 242.   Mr. Stilwell testified  that he
   purchased  a "tug" to  tow the C-123s.   Transcript at  248.  Mr.
   Stilwell  testified that  Marsh Aviation billed  Western Aviation
   for  amounts due and that Western  Aviation's obligation to Marsh
   Aviation is  reflected in  those bills, but  the record  does not
   establish that Marsh  Aviation ever submitted  a bill to  Western
   Aviation for the  tow truck or the  tow bar.  Transcript  at 159.
   As   mentioned  above,   Mr. Stilwell   testified  on   re-direct
   examination that Western Aviation's obligations were reflected in
   the exhibits  about which he testified.   Transcript at 179.  Mr.
   Stilwell never testified  about Exhibits 130 and  131, which show
   that Marsh Aviation paid for the tow truck and the tow bar.  
 
        In  support of its  post-hearing claim of  $298,550 from the
   sale  of parts  from airplanes,  Western Aviation  relies  upon a
   booklet titled,  "Marsh Aviation  Company, Falcon  Field Airport,
   Mesa,  Arizona, Proposed Purchase  of Fairchild C-123  and C-123T
   Aircraft."  The booklet is  dated February 15, 1996, and contains
   Marsh Aviation's cash flow projections, based upon the assumption
   that  it  acquired  the  C-123s that  GSA  advertised  for  sale.
   Western Aviation  is not mentioned  in the booklet.   The booklet
   contains a cash flow projection  showing sales prices and cost of
   sales  of the  engines and  propellers from  the airplanes.   The
   amount  claimed by Western Aviation  in its post-hearing brief is
   the difference between the projected  sales prices of engines and
   propellers, and the projected cost of sales,  without taking into
   account the projected  acquisition cost of  $72,500.  The  amount
   claimed  is overstated  by $3150  because  it includes  projected
   profits from an  airplane that Western Aviation  did not purchase
   instead  of  projected  profits  from  an airplane  that  it  did
   purchase.[foot #] 5      Of  the   amount   claimed  by   Western
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 5 The two  airplanes are  identified on  page 6  of
   Exhibit  109  as  Item  10 (the  airplane  that  Western Aviation
   purchased) and Item  11 (the airplane  that Western Aviation  did
   not purchase).
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   Aviation, Marsh  Aviation projected  receiving $200,000 from  the
   sales of propellers.   Marsh  Aviation explained  in the  booklet
   that the propellers would sell for  this amount only if they were
   modified to be installed on a different type of airplane.  An FAA
   supplemental  type certificate  would be  needed  to permit  this
   modification  and  installation.   Without  such a  modification,
   Marsh Aviation  said that  the value of  the propellers  was low.
   The  booklet  contains  a general  disclaimer,  stating  that the
   projected  sales  and  cost  of  sales,  though  believed  to  be
   accurate,  were  not guaranteed.    Exhibit  109.   Mr.  Stilwell
   testified that  Marsh Aviation had  a buyer for the  engines, and
   that if Marsh Aviation instead of Western Aviation had sold these
   items,  the companies'  books would  have  been straightened  out
   later.  Transcript at 173-74.  There  is no evidence to show what
   the buyer for the engines was willing to pay,  or to show that an
   FAA supplemental type certificate was ever obtained to permit the
   propellers to be installed on a different type of airplane.  
 
 
        In support of  its post-hearing claim of a  profit of either
   $3.5 to $18 million for sale of the airplanes or $4.9 for leasing
   the airplanes,  Western Aviation relies  upon a booklet  that was
   jointly  prepared by Marsh Aviation and Firestar Aircraft Company
   in August  1996, for the  purpose of attracting investors  to the
   project described in the booklet, which was to convert four types
   of  airplanes, including  C-123s,  into fire  fighting  aircraft.
   Exhibit 110;  Transcript at 131. The booklet  explains that Marsh
   Aviation had achieved  substantial industry recognition,  as well
   as  operational and financial success, in designing and producing
   aerial  fire fighting  aircraft and  components,  and that  Marsh
   Aviation had a proven track record of obtaining FAA certification
   for its products and selling  converted airplanes for use in fire
   fighting.   The  booklet says  that Marsh  Aviation  and Firestar
   Aircraft Company owned the airplane conversion program.  It never
   mentions Western Aviation, and speaks only of the manner in which
   Marsh  Aviation  and  Firestar  Aircraft  would  utilize  C-123s.
   Exhibit 110. 
 
        The August  1996 booklet  estimates that  the C-123  project
   would cost $6.5 million to complete, that converted  C-123s could
   each be  sold for  between $5 and  $9 million depending  upon the
   components ordered by  the customer, and that an operating profit
   of 40% would be realized on each sale.  Exhibit 110 at 86, 90-91.
   The   record   contains   no  evidence   of   Western  Aviation's
   profitability.  Western Aviation's post-hearing claim for between
   $3.5 and $18 million for sales is calculated as follows.  If five
   airplanes each  sold for between  $5 and $9 million,  total sales
   would be  between $25 and  $45 million.  Multiplying  these sales
   figures by an operating profit of 40% would  result in profits of
   between $10 and $18 million.  If the entire $6.5  million project
   completion  cost  is   attributed  to  sales  of   airplanes  and
   subtracted  from these figures,  the profits realized  from sales
   would range from $3.5 million to $11.5 million.  So, in its post-
   hearing brief, Western  Aviation claims that  the least it  could
   have expected to profit from the sale of five  airplanes was $3.5
   million, and the most it  could have expected to profit  from the
   sale was $18 million.   The booklet does  not, however, say  that
   five  airplanes would  be sold.    To the  contrary, the  booklet
   states that  four of the  five airplanes owned by  Marsh Aviation
   would  be leased  for fire fighting.     Exhibit 110 at  87.  The
   booklet estimates that the net operating profit of a C-123 leased
   for  ninety days  would  be  $432,250 in  the  United States  and
   $571,900 in other  countries.  Assuming  that all five  airplanes
   could  be leased  for  one year  (four  ninety-day periods),  the
   expected annual operating  profit of all five  airplanes would be
   between  $8,645,000 and  $11,438,000.   Exhibit 110  at 92.   Mr.
   Stilwell  explained that  airplanes are  usually  used from  June
   through  mid-September in the northern hemisphere.  Transcript at
   135.   If  the entire  $6.5  million project  completion cost  is
   attributed  to  leases  of airplanes  and  subtracted  from these
   figures, the profits realized from leasing would  range from $2.1
   million to $4.9 million.[foot #] 6  
 
 
                               Discussion
 
        The  contracting officer  had the  authority  to enter  into
   contracts with Western Aviation, and GSA breached those contracts
   when  it failed  to turn  over  the five  airplanes that  Western
   Aviation purchased.   If Western Aviation is  entitled to recover
   monetary damages, the  amount of those damages is  not limited by
   the exculpatory  clauses contained in the contracts.   The amount
   recoverable  is  limited,  however,  to  damages  that  were  the
   foreseeable result  of a breach  at the time the  parties entered
   into  their  contracts and  that  can be  proved  with reasonably
   certainty.
 
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 6 In  its  post-hearing brief,  Western  Aviation's
   estimated profits  from leases  are based  upon figures  found at
   pages  93  and  94  of  Exhibit 110.    These  figures,  however,
   represent the  estimated profits  from sales  plus the  estimated
   profits from leases.  
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   The Contracting Officer's Authority
 
 
        According to  statute and  regulation, contracting  officers
   have the authority to enter  into contracts.  41 U.S.C.    601(3)
   (1994);  48 CFR  2.101  (1995).     The  contracting officer  who
   awarded  the contracts  to Western  Aviation  held a  contracting
   officer's  warrant  of   appointment  and  his  duties   included
   disposing of property  that had been screened, as  had the C-123s
   at issue here,  to determine that  it was  not needed by  another
   Government agency and  that there was no qualified  party to whom
   the Government could  donate the property.  There  is no evidence
   that  the  contracting  officer's warrant  itself  contained  any
   language that limited  his authority to enter into  the contracts
   with   Western  Aviation.     According  to  GSA,   however,  the
   contracting  officer lacked  the authority  to  enter into  these
   contracts.   
 
        GSA  argues that  the  contracting officer's  authority  was
   limited by the Defense Reutilization and Marketing Manual because
   the manual did  not list C-123s as  items available for sale  for
   commercial  use at the time of  the sale to Western Aviation, and
   was also limited  by GSA regulations that prohibit  selling items
   that are  contaminated  with hazardous  materials.   Respondent's
   Post-Hearing Brief at  21-27.  We do not  accept GSA's arguments,
   as explained below.
 
        The Defense Reutilization and Marketing Manual
 
        We  find  no  language  in  the  Defense  Reutilization  and
   Marketing  Manual  that  limited  the  GSA contracting  officer's
   authority    to    enter     into    contracts    with    Western
   Aviation.[foot #] 7      The   manual   contained   a   list   of
   airplanes that could be sold for commercial use and, at the  time
   of the  sale to  Western Aviation,  the C-123 was  not among  the
   airplanes  listed.   The  manual,  however, was  an  internal DoD
   document and said that it applied  to DoD activities.  The manual
   did not say that it applied to anyone employed by an agency other
   than DoD, and did not mention the authority of a  GSA contracting
   officer to sell surplus property.  
 
        In addition to  the manual's lack  of an express  limitation
   upon a GSA contracting officer's  authority, there is no evidence
   to show  that  DLA, the  agency  that determines  DoD's  property
   disposal policy  and that  issued the  Defense Reutilization  and
   Marketing Manual, read the  manual as limiting a GSA  contracting
   officer s authority  to sell C-123s  for commercial use.   Before
   the sale at  issue here, GSA consulted with the  DLA employee who
   was  responsible  for   maintaining  and  issuing  the   list  of
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 7 Although  our record does  not contain a complete
   copy of the manual, the parties  placed portions of the manual in
   the record, and  those portions are presumably the  ones that are
   relevant to this case.  
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   commercially  salable airplanes, about  the salability of  the C-
   123s.  He told GSA that a decision had  been made to classify the
   C-123 as  commercially salable and  that this  decision would  be
   shown in the  manual the next time  it was revised.   There is no
   evidence   that  this  DLA  employee  believed  that  the  manual
   restricted the authority of GSA's contracting officer to sell the
   C-123s.  Neither  is there any evidence that  the GSA contracting
   officer  or any  of  his  supervisors  believed that  the  manual
   imposed a limitation upon his authority.  
 
 
        GSA  points out that  the Air Force  read the manual  to say
   that the  sale of the  C-123s by GSA  for commercial use  was not
   authorized.  The Air Force's  interpretation of the manual is not
   persuasive, however,  because the  Air Force  was not the  agency
   responsible for either determining  the property disposal  policy
   of DoD or  maintaining the manual.   In addition,  the Air  Force
   first  provided GSA with its view of the manual nine months after
   the sale,  when it  was attempting to  persuade GSA  to terminate
   Western  Aviation's  contracts.    Also,  after  expressing  this
   opinion,   the  Air  Force  continued  to  consider  whether  the
   airplanes  could  be  released  to  Western  Aviation,  which  is
   inconsistent  with reading the  manual to say  that it eliminated
   the GSA contracting officer's authority to sell the C-123s.  
 
        In summary,  we find no  facts to support the  argument that
   the  Defense Reutilization and  Marketing Manual limited  the GSA
   contracting officer's  authority.   Although the  manual did  not
   list C-123s as items available for sale for commercial use at the
   time of the sale to Western  Aviation, the manual applied to  DoD
   activities and did not impose any express limitation upon the GSA
   contracting  officer's authority.    In  addition,  there  is  no
   evidence that  either DLA  or GSA read  the manual  as containing
   such  a limitation.   For  these  reasons, we  conclude that  the
   contracting  officer's authority was  not limited by  the Defense
   Reutilization and Marketing Manual.
 
        The Hazardous Materials Regulations
 
        Although published regulations provide that agencies  cannot
   dispose of items  that are contaminated with  hazardous materials
   without    following     certain    procedures,[foot #] 8     the
   evidence  does not  establish  that the  five  airplanes sold  to
   Western Aviation were contaminated.   The airplanes in which  Air
   Force  employees smelled chemical odors and experienced a burning
   sensation were  not among  those sold to  Western Aviation.   The
   record does  not establish  whether any  of the  Western Aviation
   airplanes were  tested for dioxin.   Two of the  Western Aviation
   airplanes   were  not  tested  to  determine  whether  they  were
   contaminated  with 2,4-D or  2,4,5-T.  Even  though swipe samples
   were taken from the remaining three Western Aviation airplanes in
   the areas most likely to be contaminated with the two herbicides,
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 8 41 CFR pts. 101-42, -45 (1995).
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   if  there was  any amount  of 2,4-D  and  2,4,5-T present  in the
   samples from one  airplane, it was below detectable  levels.  For
   each  of the  other  two Western  Aviation airplanes,  one sample
   showed detectable levels  of herbicides and the other  sample did
   not.  The  laboratory that analyzed the samples  for the presence
   of  2,4-D  and 2,4,5-T  noted  that  the  presence of  these  two
   herbicides did  not establish that  dioxin was present.   The Air
   Force toxicologist who studied the results of the tests  believed
   that there was  some dioxin in the airplanes,  but concluded that
   the level of  contamination of individual airplanes  was unknown.
   Although  he  recommended  that  a  minimum of  ten  samples  per
   airplane be taken and analyzed in order to determine the level of
   contamination  of the airplanes,  no further samples  were taken.
   The record  contains conflicting evidence  as to how many  of the
   airplanes sold to  Western Aviation were used  in Southeast Asia,
   and does not establish whether any of the airplanes were  used to
   spray Agent Orange.  Similarly, the evidence is conflicting as to
   whether  the  five  Western  Aviation  airplanes  contained spray
   equipment at the time of the sale or at any prior time.  
 
 
        GSA  contends  that   even  though  some  tests   showed  no
   detectable  levels of herbicides, this does not establish that no
   dioxin  was  present  because  there  is  no  "minimum  level  of
   contamination for  dioxin."   Respondent's Post-Hearing  Brief at
   25.   In other  words, even though  testing showed  no detectable
   levels  of  herbicides, this  did  not establish  the  absence of
   dioxin and so the airplanes were contaminated and should not have
   been  sold.  We  reject GSA's contention.   If we  were to follow
   GSA's logic, all surplus property  would have to be considered to
   be  contaminated  with  dioxin  because  even  if  it  showed  no
   detectable  levels of 2,4-D and 2,4,5-T, this would not establish
   the absence of dioxin.  
 
        In  summary, the evidence  does not establish  that the five
   airplanes  sold  to  Western  Aviation   were  contaminated  with
   hazardous materials, so  we cannot conclude that  the contracting
   officer's authority to enter into contracts to sell the airplanes
   was limited by  regulations concerning the disposal  of hazardous
   materials.   
 
   Breach of Contract
 
        Unless some contract  provision authorized GSA to  refuse to
   turn over the  five airplanes to  Western Aviation, GSA s  action
   constitutes a breach of contract.  Binding contracts existed when
   GSA  sent  Western Aviation  notices  of  award.   The  contracts
   provided  that  Western  Aviation  was  entitled  to  obtain  the
   airplanes when  it paid  for them in  full, and  Western Aviation
   satisfied this  requirement.   The only  restriction placed  upon
   Western Aviation s right  to obtain the  airplanes after it  paid
   for them was set out in  the invitation for bids, which  provided
   that Western Aviation had to arrange for a removal date and time.
   Although Western Aviation did not remove the airplanes, this  was
   due  to the actions  of GSA and  not due to any  fault of Western
   Aviation.   GSA told  Western Aviation that  it could  not remove
   three of the five airplanes.   Although GSA gave Western Aviation
   permission to remove the remaining two airplanes, GSA effectively
   rescinded  that permission when  it terminated the  contracts for
   those airplanes.[foot #] 9  
 
 
        The Description Warranty clause contained  in the invitation
   for  bids authorized  GSA to  retain the  airplanes if  they were
   misdescribed in  the invitation.   The  invitation described  the
   airplanes as C-123s, which is  correct, and accurately listed the
   serial numbers of the airplanes.   Because the airplanes were not
   misdescribed in the invitation for bids, the Description Warranty
   clause did  not  authorize GSA  to  withhold the  airplanes  from
   Western Aviation.  
 
        GSA argues that it was authorized to refuse to turn over the
   airplanes by the Withdrawal of Property After Award clause, which
   permitted the Government to retain the airplanes  for its use . .
   . if a bona fide requirement  for the property develops or exists
   prior to actual removal of the property from Government control. 
   Exhibit 2.   GSA contends  that it was permitted  to withhold the
   airplanes  from Western Aviation  because the clause  permits the
   Government to  withdraw  property  in order  to  save  money  and
   permits the Government to withdraw property after award unless it
   does so with the intent to resell it.   Respondent's Post-Hearing
   Brief at 31-33.  
 
        In support  of its  reading of the  clause, GSA  relies upon
   Peck Iron &  Metal Co. v.  United States, 496  F.2d 543 (Ct.  Cl.
   1974),  and Convery  v.  United  States, 597  F.2d  727 (Ct.  Cl.
   1979).[foot #] 10      In   Peck,  the   Court   held   that  the
   clause did  not  permit  the Government  to  withdraw  an  entire
   aircraft  carrier  when  it  needed  only a  small  part  of  the
   carrier's  equipment and intended  to resell the  remainder.  The
   Court  stated  that  the  clause  was meant  to  apply  when  the
   Government  actually  needed  the property  to  use  for  its own
   purposes,  and not when  it intended to resell  the property.  In
   Convery,  the  Court decided  that  an  agency  had a  bona  fide
   requirement  for a  machine that  it used as  a trade-in  when it
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 9 If  GSA  had   wanted  to  terminate  these   two
   contracts based  upon Western  Aviation's failure  to remove  the
   airplanes, it would have needed to send Western Aviation a notice
   of default,  as provided  in Standard  Form  114C, General  Sales
   Terms and Conditions.  GSA  did not terminate these two contracts
   based  upon  Western   Aviation's  failure  to  remove   the  two
   airplanes.  
 
        [foot #] 10 GSA  also  cites  to  Chesapeake Salvage  Corp.,
                                          _________________________
   ASBCA  24861,  81-1  BCA    15,020.   Although  the  board  there
   discussed  the  Withdrawal  of Property  After  Award  clause, it
   explained that the  clause was not involved in  that case because
   the agency did not withdraw any property from the award.
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   purchased a new machine that was badly needed.  The Court decided
   that the agency did not have to  establish that it had a physical
   use  for the  withdrawn property,  and it  found support  for its
   decision  in a  statute that  permitted  agencies to  acquire new
   property by  using old  property for a  trade-in allowance.   The
   Court  also noted  that  using  the old  machine  for a  trade-in
   resulted in a substantial savings to the Government. 
 
 
        Consistent with the  language of the Withdrawal  of Property
   After Award clause, Peck and  Convery establish that although the
   clause does not require the Government to have a physical use for
   withdrawn property, it does require that the Government have some
   use for property that it withdraws from award, due to a bona fide
   requirement for  the property.   The cases  do not hold  that the
   clause permits  the Government  to withdraw  property from  award
   unless it  does so  with the  intent to  resell it,  or that  the
   Government may withdraw property simply to save money.  According
   to Peck, when  the Government intends to resell  property that it
   withdraws after award, it is not withdrawing the property for its
   use due to the  existence of a bona fide requirement.   According
   to Convery, when the Government intends to use withdrawn property
   as  a valuable  trade-in for  badly  needed new  property, it  is
   withdrawing the  property for its use  due to the  existence of a
   bona fide requirement. 
 
        In addition to Peck and Convery, other decisions explain the
   circumstances  in which  the  Government will  be  found to  have
   withdrawn property  for its use  due to the  existence of a  bona
   fide requirement.   For example,  the Government had a  bona fide
   requirement to  use five  scrap armored  personnel carrier  hulls
   that the Marine Corps planned to convert  to heavy duty tank hull
   trailers (Coast Iron & Metal Co., ASBCA 14082, 70-2  BCA   8392);
   a refueling tank from a truck when half of the refueling tanks at
   one Air Force  base were inoperable (Garry E.  Pugh, ASBCA 25819,
   82-2  BCA     15,834);  a  machine  that  the  Navy  intended  to
   incorporate into  its anchor  chain testing program  (Coordinated
   Equipment  Co., ASBCA  27164,  83-2 BCA     16,555); and  antenna
   controls that the Defense Nuclear Agency needed to use to fulfill
   a treaty commitment (Eric Bjorgum, ASBCA 49988, 00-1 BCA   30,695
   (1999)).  The  Government did not have a bona fide requirement to
   use a  brake press machine that  it withdrew from a  sale because
   the machine should  never have been included  in the sale in  the
   first place (Merchants and Traders Group, Inc., ASBCA 15993, 71-2
   BCA   8960), or a gun turret that it withdrew from a sale because
   the invitation for bids  inaccurately stated the demilitarization
   requirements and  the weight  of the  turret (Clyde  Kirby, ASBCA
   20558, 76-2 BCA   12,059).
 
        GSA has not established that it withdrew the airplanes after
   award for  the Government s use  due to the  existence of a  bona
   fide requirement  for the airplanes.   GSA contends that  the Air
   Force had  a bona fide  need for  the airplanes because  it would
   have been costly to test them thoroughly and because it needed to
   protect  the  public   by  preventing  the  release   of  dioxin-
   contaminated airplanes.  Respondent's  Post-Hearing Brief at  31-
   33.   As explained earlier  in our discussion of  the contracting
   officer's authority, GSA  has not established that  the airplanes
   purchased by Western Aviation were contaminated.  The Air Force's
   concerns  about the  cost of  testing do  not establish  that the
   Government  actually made  any  use of  the  airplanes because  a
   requirement  existed  for  them,  and so  these  concerns  do not
   provide  a basis  for applying the  Withdrawal of  Property After
   Award  clause.  The contracting officer correctly understood that
   the Air Force did not have any need for the airplanes and that it
   intended to  seal them  and store them.   None  of the  precedent
   concerning  the Withdrawal of  Property After Award  clause would
   support a conclusion that sealing and storing an airplane amounts
   to using an  airplane.   So far  as our record  shows, no  agency
   developed any bona fide requirement  for the airplanes and no one
   is making any use of them.  In such circumstances, the Withdrawal
   of Property After Award clause did not authorize GSA to refuse to
   turn over the airplanes to Western Aviation.
 
 
        GSA s  refusal to permit Western Aviation to take possession
   of the  airplanes constitutes a  breach of  contract because  the
   contract  entitled Western Aviation to the airplanes when it paid
   for them in full, which it did,  and when it made arrangements to
   pick them up, which it was prevented from doing by GSA.  Although
   the Description Warranty  clause contained in the  invitation for
   bids and the Withdrawal of Property After Award clause  contained
   in  the  General  Sale Terms  and  Conditions  authorized  GSA to
   withdraw the airplanes from the sale in some circumstances, those
   circumstances were not present in this case.  
 
   Availability of Monetary Damages and Applicability of Exculpatory
   Clauses
 
        A  Government agency can  have the best  possible motive for
   deciding  not to  fulfill the  terms of  a contract,  but  a good
   motive  does   not  eliminate  the  agency s  responsibility  for
   compensating the  contractor for  a breach.   In  Everett Plywood
   Corp.  v.  United  States,  651  F.2d 723  (Ct.  Cl.  1981),  the
   Government   terminated  a   contract   due  to   concerns  about
   environmental damage.   In  considering whether  the Government s
   desire to protect the environment  meant that it could cancel the
   contract  without  being  liable for  breach  damages,  the Court
   explained:
 
        There can  therefore be no  doubt that high  reasons of
        public  policy  do  not  endow  public  officials  with
        authority  to  repudiate  contracts,  though  they  may
        influence courts to refrain from interference by way of
        specific performance,  etc., and from  awarding damages
        that  exceed  a  reasonable compensation  for  the lost
        contract rights. 
 
        . . . .
 
        Clearly, the government ought not to have stood idly by
        and continued with the contract if  unacceptable damage
        to  the environment were foreseen.   On the other hand,
        whether the  government can terminate  the contract and
        escape making compensation is  another issue, the issue
        we are concerned with.
 
   651 F.2d at  728, 729.  Accord Sun Oil Co.  v. United States, 572
   F.2d 786 (Ct. Cl. 1978).   The issue that concerned the Court  in
   Everett  Plywood is  also  the  issue that  concerns  us in  this
   appeal.
 
        Even though  the  Air  Force  suspected  that  some  of  the
   airplanes sold to  Western Aviation might have  been contaminated
   with a hazardous  substance, GSA s actions constituted  a breach.
   Although  Western Aviation  is not  entitled  to obtain  specific
   performance of  its contract, Western Aviation  Maintenance, Inc.
   v.  General  Services  Administration, GSBCA  14165,  98-2  BCA  
   29,816,  Western Aviation  might  be  able  to  collect  monetary
   damages.   Before  we  examine  Western  Aviation's  request  for
   damages,  however, we first determine whether any contract clause
   limits the amount of Western Aviation's recovery.
 
        In certain  circumstances, the  Description Warranty  clause
   and the  Withdrawal  of Property  After  Award clause  limit  the
   amount of money damages that a contractor can recover to a refund
   of whatever  amount the contractor paid to  GSA.  When a contract
   contains clauses such  as these, the Government s  ability to use
   them to limit its liability is curtailed by the strict and narrow
   construction of the clauses.  If the facts of a case do not bring
   it within the  confines of the clauses, however,  the limitations
   on liability  contained in the  clauses do not apply.   Peck Iron
   and Metal  Co. v.  United States, 496  F.2d 543  (Ct. Cl.  1974);
   Benjamin v.  United States, 348 F.2d 502 (Ct. Cl. 1965); Deep Run
   Salvage, ASBCA 45152,  94-1 BCA    26,371 (1993) (denying  motion
   for summary relief); Clyde Kirby, ASBCA 20558, 76-2 BCA   12,059;
   Merchants and Traders Group, Inc.,  ASBCA 15993, 71-2 BCA   8960.
   As explained in the previous section of this opinion, GSA did not
   misdescribe the  C-123s and did  not withdraw them from  the sale
   for  the Government's  use due  to the  existence of a  bona fide
   requirement   for  the  airplanes,  so  neither  the  Description
   Warranty clause nor the Withdrawal of Property After Award clause
   operates to limit the amount  of Western Aviation's recovery to a
   refund of its purchase price. 
 
        The Limitation on Government s Liability clause can, in some
   circumstances, limit recovery to a refund of the amount paid by a
   successful bidder.  The Government cannot, however, always  use a
   limitation  on liability clause to limit its liability for breach
   damages  to a refund, because the use of the clause is restricted
   by public  policy  considerations and  fundamental principles  of
   contract law that require contracts to be  supported by mutuality
   of obligation and consideration that is not illusory.  The clause
   was designed to be used to limit the Government s  liability to a
   refund when   (1) a need for  the property develops  after it has
   been  declared surplus  and offered  for sale,  or (2)  a serious
   mistake has been made, such  as a grave price discrepancy between
   the true  value of  the item and  the amount  bid.    Freedman v.
   United  States, 320  F.2d 359, 362  (Ct. Cl.  1963).   The clause
   should not  be construed  as  absolving  the Government  from all
   damages  where it breaches  the contract,  without  having one of
   the two good reasons enumerated above, because to read the clause
   as completely relieving  the Government for liability  for breach
   damages "would come close to (if not reach) the pit of voidness. 
   Id.  at 366.   Accord Thuresson v.  United States, 453  F.2d 1278
   (Ct. Cl. 1972);  Stoner-Caroga Corp. v. United States,  3 Cl. Ct.
   92 (1983).  
 
 
        The  Limitation on  Government's Liability  clause  does not
   limit Western Aviation's recovery to  a refund of the amount that
   it paid to  GSA.  As  discussed in the  previous section of  this
   opinion, no  Government need for  the C-123s developed  after the
   airplanes  were  declared surplus  and  offered  for sale.    GSA
   contends that it  made a serious mistake when it sold the C-123s,
   because  the Defense Reutilization  and Marketing Manual  did not
   list that  type of airplane  as commercially salable at  the time
   the sale to Western Aviation occurred.  Respondent's Post-Hearing
   Brief  at 33-34.  The evidence does  not show that the provisions
   of the  manual applied  to sales  made by  GSA, and  so does  not
   establish that the GSA contracting officer made a mistake when he
   sold the C-123s.   DLA authored  the manual and the  DLA employee
   who  maintains  and  issues  the  list  of  commercially  salable
   airplanes told GSA  before the sale that a decision had been made
   to classify the  C-123 as commercially salable and  that it would
   be listed as such the next time the manual was revised,  which it
   was.  There is no evidence that  any DLA or GSA employee believes
   that it was a mistake  to sell the C-123s.  We  are not convinced
   that  GSA made  a mistake, much  less a serious  mistake, when it
   advertised and  sold the C-123s.   In addition, given  the public
   policy considerations that caution against a broad application of
   the  clause, it  is  not surprising  that  no precedent  supports
   invoking the  Limitation on  Government's Liability  clause based
   upon  a mistake such as  the one that  GSA contends occurred here
   concerning   a   limitation   upon  the   contracting   officer's
   authority.[foot #] 11
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 11 When  a   contracting  officer's   authority  is
   limited by either a statute or a regulation published in the Code
   of Federal Regulations, disregard of that limitation is a mistake
   serious enough  to void the terms  of a contract.   Total Medical
                                                       _____________
   Management, Inc.  v. United States,  104 F.3d  1314 (Fed.  Cir.),
   __________________________________
   cert. denied, 522  U.S. 857 (1997); Urban Data  Systems v. United
   ____________                        _____________________________
   States,  699  F.2d   1147  (Fed.  Cir.  1983).    Absent  unusual
   ______
   circumstances, however, disregard  of a limitation imposed  by an
   unpublished, internal agency directive is not so eventful.  Texas
                                                               _____
   Instruments Inc. v. United States, 922 F.2d 810 (Fed. Cir. 1990);
   _________________________________
                                                      (continued...)
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   Western s Damages
 
 
        As explained  in our  findings of  fact, Western  Aviation's
   damages claims  have been revised  several times.  We  accept the
   version of the claim set  out in Western Aviation's opening post-
   hearing brief as the final revision of its claim.  In that brief,
   Western Aviation argues that it is entitled to recover either its
   expectation interest  damages or  its reliance interest  damages.
   The expectation  interest  damages claimed  by  Western  Aviation
   consist of its potential profits from sales of airplanes ($3.5 to
   $18 million), sales of parts ($298,550),  and leases of airplanes
   ($4.9 million).  The reliance interest damages claimed by Western
   Aviation  amount to $745,000.57,  which consists of  $318,400 for
   salaries, moving expenses,  travel expenses, and legal  expenses,
   and  $28,468.63  for  parts  as set  out  in  Western  Aviation's
   September 4, 1998 letter to GSA counsel; plus $369,825 for labor,
   $20,686.94 for computer  costs, and $7620  for equipment to  move
   airplanes as set  out in Western Aviation's  opening post-hearing
   brief.         Appellant's    Post-Hearing    Brief     at    44-
   45.[foot #] 12  
 
        Expectation interest  damages and reliance  interest damages
   are  available as  alternative forms  of  recovery.   Expectation
   interest damages  give a non-breaching  party the benefit  of the
   bargain by  placing it  in as good  a position  as it  would have
   occupied  if  the  breaching party  had  performed  the contract.
   Expectation interest  damages  can  include  profits.    Reliance
   damages  include  expenditures the  non-breaching  party  made in
   performance or  in anticipation  of performance  of the  contract
   that was breached.  Reliance interest damages reimburse  the non-
   breaching  party for  the loss  caused by  its reliance  upon the
   contract by placing the  party in as good a position  as it would
   have  occupied if  the contract  had never  been made.   Reliance
   interest damages do not include  profits.  Laka Tool and Stamping
   Co.  v. United States, 650 F.2d 270  (Ct. Cl.), cert. denied, 454
   U.S.  1086 (1981);  ATACS Corp.  v.  Trans World  Communications,
   Inc.,  155 F.3d 659,  669 (3rd Cir.  1998); Landmark  Land Co. v.
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 11 (...continued)
   Howard  Nettleton, PSBCA  3454, 94-3  BCA    27,038;  A-1 Garbage
   _________________                                     ___________
   Disposal & Trash Service, ASBCA 30623, 89-1  BCA   21,323; Kurz &
   ________________________                                   ______
   Root Co., ASBCA 17146, 74-1 BCA   10,543.
   ________
 
        [foot #] 12 Western Aviation  does not claim  the difference
   between the fair market value of the airplanes at the time of the
   breach and the  contract price,  which would  be the  traditional
   measure  of damages for  a breach such  as occurred  here.  Globe
                                                               _____
   Refining Co. v. Landa Cotton Oil Co., 190 U.S. 540 (1903); Miller
   ____________________________________                       ______
   v. United  States, 140 F. Supp. 789 (Ct. Cl. 1956).  This is just
   _________________
   as well, however, because there  is no evidence to establish that
   there was  any difference  between the fair  market value  at the
   time of the breach  and the contract price, and GSA  refunded the
   contract price after it terminated the contracts.  
 
                   ----------- FOOTNOTE ENDS -----------
 
 
   United States, 46 Fed. Cl. 261 (2000); California Federal Bank v.
   United States,  43 Fed. Cl.  445 (1999); Dolmatch Group,  Ltd. v.
   United States,  40 Fed. Cl.  431 (1998); Restatement  (Second) of
   Contracts    344, 349 (1981).  
 
 
        In  order  to  recover  for breach  of  contract,  the  non-
   breaching  party must establish  that its damages  were caused by
   the  breach.    The  principle  of  legal  causation  employed in
   contract  cases is  foreseeability, much  the  same as  proximate
   cause  is the principle used in  most tort cases.  Breach damages
   are recoverable only  if, at the time the  contract was made, the
   breaching party had reason to  foresee that such damages were the
   probable result of  a breach.  Damages are  foreseeable either if
   they are the natural and ordinary  consequence of a breach, or if
   they  are due  to special  circumstances of  which the  breaching
   party was aware at the time of contracting.  Exxon Co., U.S.A. v.
   Sofec, Inc.,  517 U.S.  830, 839-40 (1996);  Wells Fargo  Bank v.
   United States, 88  F.3d 1012 (Fed. Cir. 1996),  cert. denied, 520
   U.S. 1116 (1997); Landmark Land Co. v. United States, 46 Fed. Cl.
   261 (2000); California Federal Bank v. United States, 43 Fed. Cl.
   445 (1999);   S.N. Nielsen  Co., GSBCA 4916,  81-1 BCA    14,921;
   Hadley  v. Baxendale, 156  Eng. Rep. 145  (Ex. 1854); Restatement
   (Second) of  Contracts    344, 351 (1981).  Lost profits that the
   non-breaching party  claims it  would have  realized from   other
   independent   and  collateral    contracts,   if  not   for   the
   Government s breach, are not recoverable because such profits are
   not directly caused  by the breach  and are not  the natural  and
   ordinary consequence of the breach.   Myerle v. United States, 33
   Ct. Cl. 1, 26 (1897); Wells Fargo  Bank v. United States, 88 F.3d
   1012 (Fed. Cir. 1996), cert. denied, 520 U.S. 1116 (1997); Morris
   v. United States,  39 Fed.  Cl. 7  (1997), aff'd,  178 F.3d  1307
   (Fed. Cir. 1998) (table).
 
        In  addition  to  being  recoverable only  if  they  are the
   foreseeable  result of a  breach, breach damages  are recoverable
   only  in  the  amount that  can  be  established  with reasonable
   certainty.    Reasonable  certainty  does  not mean  mathematical
   certainty.  However, in  order for the Board to make  an award of
   damages, the appellant must present sufficient evidence to permit
   us to make a "fair and reasonable approximation" of the amount of
   damages.   Locke v.  United States,  283 F.2d  521, 524  (Ct. Cl.
   1960); Restatement (Second) of Contracts   352 (1981). 
 
        Western Aviation  argues that  GSA should  be estopped  from
   denying that  the damages  sought by  Western  Aviation were  the
   foreseeable result of  a breach.  Equitable estoppel  is used "to
   bar a party from raising a defense or objection that it otherwise
   would have, or from instituting an action which it is entitled to
   institute."   American Maritime Transport, Inc. v. United States,
   18  Cl. Ct. 283, 292 (1989) (quoting Jablon v. United States, 657
   F.2d 1064,  1068 (9th  Cir. 1981)).   In  order  to establish  an
   estoppel, four elements must be present:  
 
        (1) the party  to be estopped must know  the facts; (2)
        he must  intend that his  conduct shall be acted  on or
        must so act that the party asserting the estoppel has a
        right to believe it is so intended; (3) the latter must
        be ignorant  of the  true facts; and  (4) he  must have
        relied on the former's conduct to his injury.
 
   Emeco Industries, Inc.  v. United States, 485 F.2d  652, 657 (Ct.
   Cl. 1973) (quoting United States v. Georgia-Pacific Co., 421 F.2d
   92, 96 (9th Cir. 1970)).  
 
        Western  Aviation argues  that  estoppel  should be  applied
   because (1) GSA knew in June 1996, of the expenditures being made
   by Western Aviation  and also knew at  that time that two  of the
   airplanes could be  released; (2) GSA told  Western Aviation that
   two of the  airplanes could be released and  intended for Western
   Aviation to  act upon that information; (3)  Western Aviation did
   not know that  the Air Force might not release the two airplanes;
   and  (4) Western  Aviation  spent money  in  reliance upon  GSA's
   representation that two airplanes would be released.  Appellant's
   Post-Hearing Brief at  47.  After considering  Western Aviation's
   argument, we  conclude that  there is no  basis for  applying the
   doctrine of estoppel in this case. 
 
        We are not convinced that Western Aviation  seeks to utilize
   the  doctrine of estoppel  in the  correct manner.   In  order to
   recover any damages,  Western Aviation must establish  that, when
   it entered into its contracts  with GSA, its claimed damages were
   the foreseeable result of a breach  of those contracts.  This  is
   part of Western Aviation's burden of proving its case.  Robert J.
   DiDomenico,  GSBCA  5539,  82-2  BCA    16,093  at  79,901;  G  P
   Construction  & Development Corp., ASBCA 33121, 91-3 BCA   24,302
   at 121,440.   Instead of using estoppel to bar GSA from raising a
   defense  or objection  that  it  otherwise  would  have,  Western
   Aviation wants  to use  estoppel in order  to avoid  carrying its
   burden  of  proof.    In  essence,  Western  Aviation's  estoppel
   argument is that  its damages should be recoverable  even if GSA,
   at the time  of contracting, had  no reason to  foresee that  the
   damages claimed by Western Aviation would occur in the event of a
   breach.   This  is not  the law  and we  know of no  precedent to
   support the proposition  that estoppel can work to  make this the
   law.   
 
        Even if Western Aviation is seeking to utilize the  doctrine
   appropriately,  it has  not established  the  first, second,  and
   third elements of  estoppel.  As for the  second element, Western
   Aviation has not shown that  GSA intended for Western Aviation to
   take  any  action as  the  result  of  GSA's statement  that  the
   airplanes were available to be  retrieved, other than pick up the
   airplanes.   Looking at the first and third elements, we see that
   Western Aviation has  not shown that it was ignorant of any facts
   known to  GSA.   Western Aviation correctly  states that  in June
   1996, GSA knew that  two of the five C-123s could  be released to
   Western Aviation.  Western  Aviation, however, also knew in  June
   that the  airplanes could  be released  because GSA  told Western
   Aviation that it could  come and get them.  Western Aviation says
   that in June  1996, GSA also knew of the  expenditures being made
   by Western  Aviation.   The evidence shows  that GSA  and Western
   Aviation did not  discuss the specific details  of Mr. Stilwell's
   plans for  the airplanes, although  they did discuss that  he was
   taking  measurements and proceeding to manufacture hardware.  GSA
   could  have  inferred  that Western  Aviation  was  spending some
   money, but the evidence does not establish  that GSA had any idea
   of the extent of the expenditures being made by Western Aviation.
   Western Aviation, of course, knew precisely what it was spending.
   Finally, Western  Aviation says that it did not know that the Air
   Force might not release the two airplanes.  Likewise, GSA did not
   know  that the  Air Force  might not  release the  two airplanes.
   Western Aviation has  not established that any  grounds exist for
   estopping GSA from  denying that Western Aviation's  damages were
   foreseeable.
 
 
        Expectation interest damages
 
        Western  Aviation's  claimed  expectation  interest  damages
   consist entirely of  lost profits.  It claims  that it would have
   profited from sales  of airplanes, leases of airplanes, and sales
   of parts, if not  for GSA's breach.   Damages consisting of  lost
   profits  from  sales  and  leases  of  airplanes   were  not  the
   foreseeable result of a breach,  and the amounts claimed have not
   been proved with any degree  of certainty.  Although some damages
   for lost profits from sales  of parts were the foreseeable result
   of a breach, the  amount claimed is just as uncertain  as are the
   amounts  requested for  lost  profits from  sales  and leases  of
   airplanes.
 
             Lost profits from sales and leases of airplanes
 
        Western Aviation claims  that it could  have sold or  leased
   the C-123s after it converted them to air tankers, and that GSA's
   breach caused  either $3.5  to $18 million  of lost  profits from
   sales  or $4.9  million of lost  profits from  leases.   The lost
   profits were not the foreseeable  result of a breach because they
   would have  only been  realized if Western  Aviation had  entered
   into  independent, collateral contracts for  the sale or lease of
   the airplanes.   Western  Aviation cannot  establish that  any of
   these contracts would have materialized, so it  cannot prove that
   these losses resulted  from GSA's breach.  In  addition, when GSA
   entered into the contracts to  sell the C-123s, it had  no reason
   to  anticipate that  a  breach  would cause  such  damages.   GSA
   advertised the airplanes  as scrap or salvage  airplanes, neither
   of  which is suitable  for flying.   Scrap property  has no value
   other than its basic material content.  Although salvage property
   has  some  value greater  than  its basic  material  content, its
   condition is such that its repair  cost will be more than 65%  of
   its acquisition  cost.  It  may well  be possible to  retrofit or
   upgrade any  scrap or salvage  airplane so that it  is airworthy.
   However, there was  no reason for GSA to  anticipate that whoever
   purchased  these  five  airplanes would  spend  money, especially
   before taking delivery  of the airplanes,  to prepare to  convert
   them so that they could be used for fighting fires and to develop
   a marketing program for the airplanes.  In the great multitude of
   cases  in which  airplanes are  sold  as scrap  or salvage  under
   ordinary circumstances, the consequences that occurred here would
   not, in all probability, have  occurred.  Damages resulting  from
   Western  Aviation's inability to  sell or lease  converted C-123s
   were not the foreseeable result of a breach of the contracts with
   GSA because they were not the natural consequence of  a breach of
   a contract to sell  scrap or salvage  airplanes, so they are  not
   recoverable. 
 
 
        These claimed  lost profit  damages flow  entirely from  the
   fact that Western Aviation intended to do something not generally
   done with scrap or salvage airplanes.  Not only did it  intend to
   refurbish them  for flying, it  also intended to convert  them so
   that they could be used to  fight fires and to develop a  program
   for selling and  leasing the airplanes for that purpose.   At the
   time  of  contracting,  however, GSA  was  not  aware of  Western
   Aviation's  plans.   The  contracting officer  did  not know  the
   nature of  Western  Aviation's business.    The director  of  the
   property  management division  for GSA  Region 9  spoke  with Mr.
   Stilwell  a year or so before GSA  issued the invitation for bids
   for the C-123s,  but Mr. Stilwell represented that  he worked for
   Marsh  Aviation  and  the  director  had  no  idea  what  Western
   Aviation's operations were.  GSA's property disposal and aircraft
   utilization  specialist  had  never  heard of  Western  Aviation,
   although  she  knew of  Mr.  Stilwell  and  Marsh Aviation.    No
   evidence  establishes  that  anyone from  GSA  knew  that Western
   Aviation had a  unique plan for utilizing these  scrap or salvage
   airplanes, which included refurbishing  the airplanes, converting
   them into air tankers, and then leasing or selling them.  Western
   Aviation   asserts  that  GSA's  familiarity  with  Mr.  Stilwell
   establishes  that it  knew what Western  Aviation intended  to do
   with the C-123s.   Mr. Stilwell had dealt with GSA perhaps six to
   ten  times before the  sale at issue here  and some GSA employees
   knew him as a representative of Marsh Aviation.  Even if they had
   been quite  familiar with Marsh  Aviation's business, and  we are
   not convinced  that they were,  they did not know  anything about
   Western Aviation's business.   The damages that  Western Aviation
   claims  it  incurred due  to  its  inability  to sell  and  lease
   airplanes  were not the  foreseeable result  of a  breach because
   they were due to special circumstances of which GSA was not aware
   at  the  time  of  contracting.   Thus,  those  damages  are  not
   recoverable.  
 
        Even if  lost profits from  sales and leases of  air tankers
   had  been  the foreseeable  result  of a  breach  at the  time of
   contracting,   they  would  not  be  recoverable  because  it  is
   uncertain  whether any  of  these profits  would  have ever  been
   realized or, if they had, that they would have accrued to Western
   Aviation.  In order to determine that Western Aviation would have
   realized any  profits from sales  or leases, we have  to make one
   rather important initial assumption.   That is, we have to assume
   that  Western  Aviation  would  have  been  able  to  obtain  the
   necessary FAA  approval for its  conversion of the C-123s  to air
   tankers.      Unless   the   FAA   approved   Western  Aviation's
   modifications  to the  C-123s  and  issued  a  supplemental  type
   certificate, no  projected profits  from either  sales or  leases
   would have  ever materialized.   We do  not know  whether Western
   Aviation had received such approvals in  the past, and we have no
   basis upon which to conclude  that the FAA's approval was likely.
   The estimate for lease profits includes an additional assumption,
   which is that all  of the airplanes could be leased  for 360 days
   per  year.   The usual season  for fire fighting  in the northern
   hemisphere is  only three  and one-half months,  and there  is no
   evidence to show  that it was reasonable to assume  that the five
   converted C-123s could have been leased for 360 days each year.
 
 
        The only evidence we have of projected profits from sales or
   leases  is the  August 1996  booklet that  was prepared  by Marsh
   Aviation  and Firestar  Aircraft for  the  purpose of  attracting
   investors  to a project  that involved converting  four different
   types  of airplanes to be used  for fire fighting.  The booklet's
   estimated profits from sales of converted C-123s range from a low
   of $3.5 million to a high of $18 million.  The uncertainty of the
   estimate is  evident, given its  wide range, and the  estimate is
   not supported by any evidence concerning actual  sales or expense
   data or experience.  In addition, there was no established market
   for  leasing  or  selling  converted  C-123s  for  fire  fighting
   tankers, so we do not know whether they could have been leased or
   sold as projected by Marsh Aviation and Firestar Aircraft.  Also,
   the booklet upon which Western  Aviation relies in support of its
   claim  for   lost  profits   never  mentions   Western  Aviation.
   According  to the  booklet, it  was Marsh  Aviation  and Firestar
   Aircraft that would  reap the benefits of any  sales or leases of
   the airplanes.    Finally, the  record  contains no  evidence  of
   Western Aviation's  past profits and  so, even in the  absence of
   the other  uncertainties mentioned here,  we would have  no basis
   upon which to conclude how profitable a venture the conversion of
   the C-123s might have been for Western Aviation. 
 
             Lost profits from sales of parts
 
        Western Aviation s expectation interest damages also include
   $298,550  from  the  sale  of  engines  and propellers  from  the
   airplanes.   Although it was foreseeable that  GSA s breach would
   lead to the loss of any profits to be made from the sale of parts
   from the airplanes,  Western Aviation has not  established either
   that the damages it  claims were entirely the  foreseeable result
   of  a  breach  or  that  those damages  would  have  amounted  to
   $298,550, so these damages are not recoverable.
 
        It  was  foreseeable  that if  GSA  breached  its contracts,
   Western Aviation would be damaged if it could not sell parts from
   the  scrap or  salvage airplanes  that it  purchased.   Scrap and
   salvage  items are  expected to  be  worth at  least their  basic
   material  content, so  in  the  normal course  of  events, it  is
   probable that  a purchaser would  sell the material that  made up
   the scrap  or  salvage  airplanes  and whatever  parts  could  be
   reclaimed  from the  airplanes.   As  discussed in  the following
   paragraph,  however,  the  bulk  of  Western  Aviation's  claimed
   damages   consist  of  lost   profits  from  sales   of  modified
   propellers.   Marsh Aviation  intended to modify  the propellers,
   obtain the  FAA's approval to  install them on an  airplane other
   than a  C-123, and then  sell them.   These damages were  not the
   natural and  ordinary consequence  of a breach  of a  contract to
   sell  scrap or  salvage airplanes,  and there  is no  evidence to
   suggest that  GSA was aware  of Western Aviation's  special plans
   for the  propellers.   Thus, damages consisting  of lost  profits
   from the  sale of  modified propellers  were not the  foreseeable
   result of a breach of contract.  
 
 
        In addition to not being entirely the foreseeable result  of
   a  breach, the  claimed damages  are  uncertain in  amount.   The
   support for  Western Aviation's claim  for lost profits  from the
   sale  of parts  is a  February 1996  booklet that  contains Marsh
   Aviation s  cash flow projections, based upon the assumption that
   it purchased  the C-123s from  GSA.  Western Aviation's  claim is
   overstated by $3150 because it includes projected profits from an
   airplane  that Western  Aviation  did  not  purchase  instead  of
   projected  profits from  an airplane  that it  did purchase.   In
   addition, in arriving at its claimed amount, Western Aviation did
   not subtract  the projected  cost of  acquiring  the engines  and
   propellers, which  was $72,500.   Marsh  Aviation projected  that
   $200,000  of its  projected profit  would come  from the  sale of
   propellers, but only  if the FAA would issue  a supplemental type
   certificate  to permit the modification of the propellers so that
   they  could be  installed  on  an airplane  other  than a  C-123.
   Without such a  modification, the booklet said, the  value of the
   propellers was low.   We do not  know whether the FAA  would have
   approved the propeller modification that  Marsh Aviation proposed
   and we  have no evidence of  the value of the  propellers without
   the modification.   Although  Mr. Stilwell  testified that  Marsh
   Aviation had a  buyer for the  engines, there is  nothing in  the
   record  to show whether the  price that the  buyer was willing to
   pay was anywhere near Marsh Aviation's projection, or to show how
   much Marsh Aviation would have  remitted to Western Aviation.  We
   do not know whether Western Aviation had a history of profits or,
   if it  did,  how profitable  selling the  engines and  propellers
   would have  been.  Neither  the testimony nor the  Marsh Aviation
   booklet establishes  with any  degree of  certainty what  profits
   would have  been realized by  Western Aviation from the  sales of
   engines and propellers.  
 
        Reliance interest damages
 
        Western Aviation's claimed reliance interest damages consist
   of $318,400 for  salaries, moving expenses, travel  expenses, and
   legal  expenses;  $28,468.63  for   parts;  $369,825  for  labor;
   $20,686.94 for  computer costs; and  $7620 for equipment  to move
   airplanes.   These damages  are not  recoverable, either  because
   they were not  the foreseeable result of a breach  or because the
   amount of damages was not proven with any degree of certainty.  
 
        Western Aviation claims that it spent $318,400 for salaries,
   moving expenses, travel expenses, and legal expenses in  order to
   further  the program to market refurbished C-123s as air tankers;
   $28,468.63 for parts used  to build a tank and door  system for a
   modified C-123; and $369,825 for  labor to fabricate the tank and
   door system.  These damages were not the foreseeable result  of a
   breach because they  resulted from Western Aviation's  efforts to
   convert C-123s  to air  tankers that could  be used  for fighting
   fires  and  to develop  a  marketing  program for  the  converted
   airplanes.  As explained  above in our discussion  of expectation
   interest damages, such  damages are not recoverable  because they
   were not the natural  and ordinary consequence  of a breach of  a
   contract to sell scrap or salvage airplanes, and were due instead
   to  special circumstances of which GSA was  not aware at the time
   of contracting.   In addition, to  the extent that some  of these
   costs  were  incurred  before  the  parties  entered  into  their
   contracts  and  others  were incurred  after  GSA  terminated the
   contracts, they are not damages caused by the breach.   
 
        In addition to not being the foreseeable result of a breach,
   the claimed amount of  $318,400 is uncertain.  The figure  is not
   supported by any  invoices, time sheets, payroll  records, bills,
   or any other documentary evidence  which should have been readily
   available  to  support  these  claimed  damages.    There  is  no
   testimony concerning either  the $318,400 figure or  the expenses
   that are included  within that amount.  Even if GSA had been able
   to foresee that such damages  would flow from a breach, there  is
   no evidence  to establish  the amount of  these damages  with any
   degree of certainty.
 
        The claimed amount  of $369,825 for labor is also uncertain,
   in addition to  not being the foreseeable  result of a breach  of
   contract.   This amount is  supported by a March  8, 1997 invoice
   from Marsh Aviation  to Western Aviation.   The record,  however,
   contains  two versions  of this invoice.   One shows  a charge of
   $179,600 representing  3592 hours of  work and the other  shows a
   charge of $369,825 representing 7396.5 hours of work.  The record
   does  not explain  why two  copies  of the  same invoice  contain
   different figures.   In addition,  the labor records that  are in
   evidence  contain  duplicative  entries and  do  not  support the
   number  of hours  on either  invoice, and  different records  are
   offered  to  support  the  different  versions  of  the  invoice.
   Neither version of the March 8 invoice is certain enough to serve
   as a basis for  an award of damages, even if the damages had been
   foreseeable. 
 
 
        The $20,686.94 claimed for computer costs is supported by an
   invoice for  computers purchased  months before  GSA awarded  the
   contracts to Western  Aviation; by invoices for  consulting work,
   some of which was done after GSA terminated the contracts; and by
   an invoice for  some unidentified item  that was purchased  after
   GSA terminated the contracts.  Western Aviation has not explained
   how the consulting work is related to a claim for computer costs,
   or how costs incurred before the contracts were awarded and after
   they were  terminated were the probable  result of a  breach.  In
   addition, to the extent that the computers were purchased and the
   consultants were  hired in order  to pursue a program  to convert
   the C-123s to air tankers, these damages were not the foreseeable
   result of a breach, as explained earlier in this opinion. 
 
        Finally, Western Aviation claims $7620 for a tow truck and a
   tow  bar.   The contracts  between the  parties required  Western
   Aviation to move the airplanes from  Davis-Monthan Air Force Base
   or to hire someone to move them, so it was a natural and ordinary
   result of a  breach that Western Aviation would  be damaged if it
   spent any  money in  anticipation of moving  the airplanes.   GSA
   questions whether Western  Aviation is entitled to  be reimbursed
   for the  $7620, however,  because this money  was spent  by Marsh
   Aviation.  Respondent's Post-Hearing Brief at 28.
 
        Western Aviation  asserts that  it is  liable for  the money
   that  Marsh  Aviation  spent  because  the  "undisputed  evidence
   establishes the formation of a contract between Western and Marsh
   Aviation."   Appellant's Reply  at 46.   The evidence  upon which
   Western  Aviation   relies,  however,  does   not  establish  the
   existence  of a  contract between  the two  companies that  would
   obligate Western Aviation to pay Marsh Aviation for the tow truck
   and tow bar.  Mr. Stilwell testified that Western Aviation  hires
   Marsh Aviation to  perform work for it, but that  testimony was a
   general description of the relationship between the two companies
   and did not relate either to the  five airplanes at issue here or
   to  the  tow  truck and  tow  bar.   Transcript  at  114-15.   He
   testified that Western Aviation hired Marsh Aviation to prepare a
   manual specifying  how to install  a particular engine on  the C-
   123, but this  does not evidence any contract  other than perhaps
   one to prepare the manual.  Transcript at 130.  He testified that
   Western  Aviation hired  Marsh Aviation to  design and  build the
   tank  system, and explained that Western Aviation's obligation to
   Marsh Aviation  was reflected  in the  bills that  Marsh Aviation
   sent to Western Aviation.  A contract  to design and build a tank
   system is  not a contract to purchase a  tow truck and a tow bar,
   and Marsh Aviation  never billed Western Aviation for  either the
   tow truck or  the tow bar.   Transcript at 158-59.   Mr. Stilwell
   said  that  there  was  a  signed  work  order  between  the  two
   companies,  but he  did not  know  whether there  was a  contract
   between them.  The work order is not in our record, and we do not
   know its  terms.  Transcript  at 158-59.   He testified  that the
   work of  stripping the paint  from the airplanes would  have been
   done  by  Marsh Aviation,  under  a subcontract,  and  that Marsh
   Aviation would  have probably been  the sales  agent for  selling
   parts from the  airplanes.  Nothing shows that  either a contract
   to strip paint  or to sell  parts would include purchasing  a tow
   truck or a tow bar for Western Aviation.  Transcript at 171, 174.
   Finally, in  response to a  question posed by his  counsel during
   his re-direct  examination, Mr.  Stilwell testified that  Western
   Aviation's obligations were reflected in the exhibits about which
   he testified.  This testimony is not evidence of  a contract with
   Marsh  Aviation, and  Mr.  Stilwell  never  testified  about  the
   exhibits related to the tow truck and the tow bar.  Transcript at
   179.  The evidence relied upon by Western Aviation falls short of
   establishing that it  entered into a contract with Marsh Aviation
   that  required Marsh Aviation  to purchase a tow  truck and a tow
   bar  and  also  required  Western  Aviation  to  reimburse  Marsh
   Aviation for such a purchase. 
 
 
        As  Mr.  Stilwell  explained,  Western  Aviation  and  Marsh
   Aviation  are  two separate  companies  with different  corporate
   charters.   They  conduct separate  business  operations and  use
   their separate corporate structures as the mechanism for limiting
   liability in case  of a loss.  They  vigorously maintain separate
   books and records, and Marsh Aviation billed Western Aviation for
   amounts  due to  Marsh Aviation.   The  only invoices  from Marsh
   Aviation to  Western Aviation are  dated March 8, 1997,  one year
   after Marsh Aviation  purchased the tow bar, six  months after it
   purchased  the tow  truck, two  months after  GSA terminated  the
   contracts, and six  weeks before this appeal was filed.  If Marsh
   Aviation  intended to invoice Western Aviation  for the tow truck
   and  tow bar,  it had ample  time to  do so.   Yet Marsh Aviation
   never  billed  Western   Aviation  for  either  purchase.     The
   obligations of  Marsh Aviation  do not  automatically become  the
   obligations  of Western Aviation,  even though the  two companies
   have some common ownership.  The evidence does not establish that
   Western  Aviation was obligated  to reimburse Marsh  Aviation for
   the purchase of the tow truck and the tow bar, so the evidence is
   not sufficient to establish that Western Aviation sustained $7620
   of reliance interest damages due to GSA's breach.  
 
        Summary
 
        The result in this case  might seem discordant.  Even though
   GSA  breached  its  contracts  with  Western   Aviation,  Western
   Aviation  is not  entitled to  recover any damages.  However, not
   every  breach  results  in  an   award  of  damages.  San  Carlos
   Irrigation and Drainage District v. United States, 111 F.3d 1557,
   1563 (Fed. Cir. 1997); Wells Fargo Bank v. United States, 88 F.3d
   1012, 1022 (Fed. Cir. 1996),  cert. denied, 520 U.S. 1116 (1997).
   The legal rules  that we apply in  order to reach our  result are
   not   new.[foot #] 13     Applying  those   rules,   we  conclude
   that the  evidence of  record in this  appeal does  not establish
   that Western Aviation  is entitled to recover any  of the amounts
   that it claims are due as a result of GSA's breach.  
 
                                Decision
 
        The appeal is DENIED.
   __________________________________
 
                                      MARTHA H. DeGRAFF
                                      Board Judge
 
   We concur:
   __________________________________ ______________________________
 
                                      ____
   ANTHONY S. BORWICK            ALLAN H. GOODMAN
   Board Judge                             Board Judge
 
                                                                    
                   ----------- FOOTNOTE BEGINS ---------
 
        [foot #] 13 "While  the  inquiry  we are  about  to  make is
   important,  it is by no means  a novel one, and  does not open up
   any  new field  of legal  investigation.   It  involves, not  the
   discussion of any new principle but merely the application of one
   of some  antiquity to the  actual facts  of this case."   Winston
                                                             _______
   Cigarette Machine  Co. v.  Wells-Whitehead Tobacco  Co., 53  S.E.
                   ----------- FOOTNOTE BEGINS ---------
   885, 887 (N.C. 1906).