Board of Contract Appeals General Services Administration Washington, D.C. 20405 _____________________ October 1, 1998 _____________________ GSBCA 14663-RELO In the Matter of MICHAEL D. HARAGAN Michael D. Haragan, Madison, AL, Claimant. Robert H. Garfield, Chief, General Law Division, United States Army Aviation & Missile Command, Redstone Arsenal, AL, appearing for Department of the Army. GOODMAN, Board Judge. Claimant, Michael D. Haragan, a civilian employee of the Department of the Army (Army), seeks review of the agency's denial of his request for an extension of his temporary quarters subsistence expense (TQSE) period in connection with his permanent change of station (PCS) relocation to Huntsville, Alabama. Claimant requested an extension of the TQSE period due to delay in the occupancy of his new house allegedly resulting from weather conditions, an unprecedented demand for local construction, and a labor shortage which occurred before the commencement of his initial TQSE period. The agency denied the request because claimant had entered into a contract for new construction with an anticipated completion date after the expiration of the initial period of TQSE. Claimant then filed a claim at this Board. We conclude the agency permissibly denied claimant's request. Claimant, an employee of the Army's Aviation and Troop Command (ATCOM), was relocated to Huntsville, Alabama, in a consolidation of that command into the Army's Aviation and Missile Command. This occurred as a result of the Base Realignment and Closure (BRAC) initiative. Claimant"s travel orders for a PCS move from St. Louis, Missouri to Huntsville, Alabama were dated March 21, 1997. Claimant received them on March 25, 1997. The agency authorized a ten-day househunting trip (which was accomplished April 19-26, 1997) and TQSE for an additional period of fifty days. His duty reporting date, according to the travel authorization, was July 15, 1997. On May 7, 1997, claimant signed a contract to have a house built, with a scheduled closing and possession date on or before September 15, 1997. Before his move, claimant states that personnel at his old station advised him and other employees at various briefings that extensions of the TQSE period would routinely be granted if an employee chose to build a house. The agency had issued a memorandum to all employees which advised that: The initial period of TQSE allowance . . . is authorized for a period not to exceed 60 consecutive days. . . . Authorizations to extend the TQSE period and the number of days authorized will be kept to a minimum. . . . Extensions of temporary quarters [subsistence expenses] may be authorized only in situations where there is a demonstrated need for additional time in temporary quarters due to circumstances which have occurred during the initial 60 day period of TQSE and which are determined to be beyond the employee's control. The memorandum went on to quote the various circumstances which might result in an extension of TQSE. Claimant moved to Huntsville on July 12, 1997, to accommodate his reporting date of July 15, 1997. His TQSE period commenced on July 12, 1997 and expired on September 1, 1997. He was informed by his builder on August 11 that delivery of his home would be delayed approximately thirty days, until an expected completion date of October 20, 1997. Claimant has supplied a letter from his builder dated September 9, 1997 stating that the delay was the result of adverse weather conditions in May and June, 1997, an unprecedented demand for housing in the area, and a local labor force unable to support the demand which resulted in a sixty day delay. According to the builder, but for these problems, the house would have been completed in mid to late August, 1997. After receiving notice from the builder of delay in completion of the home, claimant submitted a first request for TQSE extension to the ATCOM Civilian Personnel Office (CPO) on August 13, and his request was denied on September 2, 1997. A second request for extension was subsequently denied by the agency, as was a request for reconsideration. The basis of the agency denials was that the Joint Travel Regulations (JTR) allowed for an extension of the TQSE period only in limited circumstances. Because claimant entered into a sales contract knowing his home was not scheduled to be completed within the initial TQSE period, the agency denied his request for an extension. Discussion The JTR in effect at the time of claimant's PCS move provided that subsistence expenses beyond the initial TQSE period "may be allowed for an additional period of time not to exceed 60 consecutive days provided the head of the DOD component concerned or his/her designee, determines there are compelling reasons for the continued occupancy of temporary quarters." JTR C13004-A.2 (Aug. 1, 1995); see Thomas Potts, GSBCA 13700-RELO, 97-1 BCA  20,938. The JTR required that the employee justification and subsequent administrative approval be in writing. When an additional period of TQSE allowance is allowed, written justification and documentation must be provided. JTR C13004- A.2. The employee must provide the approving official a written justification which describes circumstances demonstrating a need for additional time in temporary quarters that occurred during the initial sixty-day period of temporary quarters occupancy and that are clearly shown to be beyond the employee's control. JTR C13004-A.3. The justification, accompanied by "documentation from the approving official indicating his/her reasons for approving or denying the requested extension[,] will be retained in a management file and available for review." JTR C13004-A.3. The General Accounting Office held that when an employee contracts to build a house with an anticipated completion date after the expiration of the initial TQSE period, any event occurring during the initial period may not be considered as having caused the employee to remain in temporary quarters beyond the initial sixty-day period. Daniel G. Colley, B-254120 (Dec. 14, 1993); Arthur P. Meister, B-224884 (Sept. 23, 1987). This Board has ruled consistent with this precedent in Bruce Park, GSBCA 14529-RELO (Aug. 4, 1998). Here, claimant signed a contract for construction of a new house with an anticipated completion date beyond the initial period of TQSE. When claimant executed the contract he was aware that the contractual completion date was after the expiration of his initial TQSE period. He states that this date was "arbitrary" and a "best guess under normal conditions and could have been accelerated just as easily as it was delayed." Nevertheless, the contract clearly specified that the builder had until a date after the expiration of the initial TQSE period to finish the house. According to claimant, one of the conditions which resulted in the delay of the completion--depletion of construction resources--occurred during the initial TQSE period. Claimant also states that one of the conditions which resulted in the request for a TQSE extension--the inclement weather leading to construction delay of claimant's new house--occurred before the initial period of TQSE. See Thomas M. Hood, GSBCA 13845- RELO, 97-1 BCA  28,954. We have consistently sustained agency denials of an extension of the TQSE period under this version of the JTR where the events allegedly causing the delay in occupancy of permanent quarters occurred outside the initial period of TQSE. Charles D. Parton, GSBCA 14462-RELO, 98-1 BCA  29,736; Michael E. Perez, GSBCA 14412-RELO, 98-1 BCA  29,608. Claimant argues that because this principle concerning contractual closing dates is "not contained in whole, in part, or inferred in" the JTR, it is therefore an "unwritten rule." He further argues that by "implementing this "rule" into agency decision criteria, disapproval of my TQSE extension is in fact contrary to written law." The agency's application of precedent established by the General Accounting Office and this Board is neither arbitrary nor capricious. Our recent decision in Bruce Park denied a claim under very similar circumstances. The claimant was an ATCOM employee whose request for an extension of the TQSE period was denied. He had purchased a home in the Huntsville area, and the construction was delayed by the same incidence of rainfall referred to by claimant in this case. Mr. Park alleged, as does claimant in the instant case, that he relied on the oral advice given at PCS briefings that extensions of the TQSE period for employees building new housing at the new duty station would be routine. We held in that case that such oral advice was unfortunate, because it was wrong. Nevertheless, despite the oral advice, the agency did hand out a written memorandum to claimant in the instant case which accurately summarized the JTR. As we have explained in an earlier matter arising from an ATCOM consolidation and relocation under the BRAC initiative, erroneous advice cannot bind the Government to spend money in violation of statute and regulation. Michael Perez. Decision The claim is denied. __________________________ ALLAN H. GOODMAN Board Judge